Quarterly Activities Report
Summary
- Lynas Rare Earths reported a quarterly gross sales revenue of A$101.2 million for Q3 FY24, down from A$242.8 million in Q3 FY23 and A$136.2 million in Q2 FY24.
- Total REO production was 3,545 REOt, and NdPr production was 1,724 REOt, matching the previous year's output.
- The average NdPr price was US$47/kg ex VAT during the quarter.
- The company strategically held approximately 500 tonnes of NdPr and all SEG inventory due to low prices.
- The Mt Weld Expansion Project is on track, with Stage 1 commissioning expected in the latter part of the calendar year.
- The Kalgoorlie facility's budget has increased to approximately A$800 million due to an extended commissioning timeline.
- Earthworks at the U.S. Rare Earths Processing Facility in Seadrift are expected to commence by the end of the calendar year, pending approvals.
- Carey Group Holdings was awarded a 5-year mining services contract at Mt Weld, commencing in April 2024.
Sentiment
Score: 6
Explanation: While production remains strong, the lower revenue and increased project costs temper the positive aspects. The strategic inventory holding and future expansion plans indicate a long-term vision, but current market conditions present challenges.
Positives
- NdPr production of 1,724 REOt matched the previous year's output.
- The Mt Weld Expansion Project is progressing as planned.
- The federal NEPA environmental approval was successfully concluded for the U.S. Rare Earths Processing Facility.
- Lynas secured a 5-year mining contract with Carey Group Holdings, a 100% First Nations-owned business.
Negatives
- Q3 FY24 revenue decreased to A$101.2 million due to low NdPr prices.
- The Kalgoorlie facility's budget increased to A$800 million due to an extended commissioning timeline.
- An exceptional rain event in early March forced the shutdown of concentrate production for several days at Mt Weld.
Risks
- Low rare earth prices could continue to impact revenue.
- Commissioning delays at the Kalgoorlie facility could further increase costs.
- Obtaining all necessary approvals for the U.S. Rare Earths Processing Facility could delay earthworks commencement.
- Reliance on external contractors like Carey Group Holdings introduces operational dependency.
Future Outlook
The company expects increased production capacity in the latter part of the calendar year as the Mt Weld Expansion Project Stage 1 circuit is commissioned, and market prices have started to improve in April.
Management Comments
- Excellent production rates, including 1,724 tonnes NdPr, were achieved in the March quarter.
- Market prices have started to increase in April.
Industry Context
The report reflects the volatility in rare earth prices and the strategic decisions companies like Lynas are making to manage inventory and production in response to market conditions; the company is investing in future production capacity.
Comparison to Industry Standards
- Lynas's strategy of holding inventory during low price periods is a common practice among rare earth producers to mitigate revenue impact.
- The increase in the Kalgoorlie facility's budget is not uncommon for large-scale projects, as commissioning and initial production often reveal unforeseen challenges and costs.
- The focus on renewable energy for the Mt Weld Expansion aligns with the growing industry trend towards sustainable mining practices.
Stakeholder Impact
- Shareholders may be concerned about the lower revenue and increased project costs.
- Employees are likely to be impacted by the ongoing expansion projects and operational changes.
- Customers may experience fluctuations in supply and pricing due to the company's inventory management strategy.
- Suppliers and creditors are likely to benefit from the ongoing expansion projects and increased operational activity.
Next Steps
- Commissioning of Stage 1 of the Mt Weld Expansion Project in the latter part of the calendar year.
- Ramping up construction of Stage 2 of the Mt Weld Expansion Project.
- Continuing commissioning and initial production activities at the Kalgoorlie facility.
- Commencing earthworks at the U.S. Rare Earths Processing Facility by the end of the calendar year, pending approvals.
Key Dates
- January 2024: Major electricity outage in Kalgoorlie.
- January 2024: Federal NEPA environmental approval process successfully concluded for U.S. Rare Earths Processing Facility.
- 14 March 2024: Carey Group Holdings awarded 5-year mining contract.
- April 2024: Carey Group commenced on site at Mt Weld.
- 31 March 2024: End of Q3 FY24.
- Late April: SMP works will commence at Mt Weld Expansion Project Stage 2.
- End of Calendar Year: Earthworks expected to commence at the Seadrift site subject to all necessary approvals being in place.
Keywords
Filings with Classifications
Production Update
- The successful first production of Terbium Oxide represents a significant expansion of Lynas' product capabilities and a positive operational milestone.
Results Presentation
- The company reports a profit in a challenging market, implying that the results were worse than expected.
Results Presentation
- NdPr production increased by 23% compared to 1H FY24.
- Sales revenue increased by 8% compared to 1H FY24.
Half Year Report
- The net profit after tax decreased significantly from $39.5 million to $5.9 million, indicating a worse financial performance compared to the previous year.
Interim Financial Report
- The results were worse than expected due to a significant decrease in net profit, driven by lower rare earth prices and increased production costs.
Quarterly Report
- The chemical inputs required for the treatment of MREC impurities were not available until December 25th, causing a delay in production.
Quarterly Report
- Production volumes were lower than planned due to issues with impurities in the MREC feedstock and the annual processing limit in Malaysia.
Annual General Meeting Presentation
- The significant increase in Mt Weld Mineral Resources and Ore Reserves, coupled with the successful completion of major projects and cost reductions, indicate results better than might have been expected.
Annual General Meeting Presentation
- Site works at the US facility are on hold due to a wastewater permitting issue.
Quarterly Report
- Rare earth prices remained low throughout most of Q1 FY25, resulting in lower than expected sales revenue compared to previous quarters.
Quarterly Report
- A permitting issue related to wastewater management has put a hold on earthworks for the U.S. Rare Earths Processing Facility.
ESG Report
- The net profit after tax was significantly lower than the previous year, indicating worse than expected financial performance.
Annual Report
- Earthworks for the planned U.S. Rare Earths Processing Facility have been delayed until a permitting issue related to wastewater management is resolved, which is unlikely to happen before the end of 2024.
Annual Report
- The net profit after tax decreased significantly from $310.7 million in FY23 to $84.5 million in FY24, primarily due to lower rare earth prices and reduced production volumes.
Company Presentation
- The company announced a 92% increase in Mineral Resources and a 63% increase in Mt Weld Ore Reserves.
Resource and Reserve Update
- The Mineral Resources and Ore Reserves have increased significantly compared to the 2018 estimates.
- The contained Dysprosium oxide in Ore Reserves has increased substantially.
- The updated Ore Reserve supports a longer mine life at expanded production rates.
Quarterly Report
- The company's REO and NdPr production were lower than the previous quarter.
Quarterly Report
- Completion of Stage 2 of the Mt Weld Expansion Project is now expected by the end of FY25.
- Delays in receiving concentrate due to disturbances to the global shipping industry and kiln maintenance shutdowns impacted downstream production.
Missing type for ID: 3288
- ASX:LYC announces a delay.
Investor Presentation
- Many new rare earth projects have stalled.
Investor Presentation
- Pricing at surprisingly low levels following strong production growth inside China.
Quarterly Report
- The commissioning timeline for the Kalgoorlie facility has been extended, leading to a budget increase.
Quarterly Report
- The Q3 FY24 revenue was significantly lower than the previous year due to lower NdPr prices and the decision to hold inventory.
Disclaimer: This summary was generated by artificial intelligence and its accuracy is not guaranteed. The information provided here is for general informational purposes only and does not constitute financial advice, recommendation, or endorsement of any kind. It may contain errors or omissions. You should not rely on this information to make financial decisions. Always seek the advice of a qualified financial professional before making any investment or financial decisions. Use of this information is at your own risk.