Quarterly Activities Report
Summary
- Lynas Rare Earths achieved a gross sales revenue of $141.2 million in the December quarter, up from $120.5 million in the previous quarter.
- Total rare earth oxide production was 2,617 tonnes, and NdPr production was 1,292 tonnes, both lower than planned due to issues in December.
- The company reached its annual lanthanide processing limit in Malaysia in late November, causing a reliance on mixed rare earth carbonate (MREC) from Kalgoorlie.
- Impurities in the MREC required additional treatment, which was delayed due to the unavailability of chemical inputs until December 25th.
- The average selling price improved to $49.2/kg, the highest since April 2023, due to strategic customer focus and favorable exchange rates.
- Market conditions remained challenging with low rare earth prices, and this is expected to continue into the March 2025 quarter.
- The Kalgoorlie facility was officially opened and Stage 1 of the Mt Weld Expansion Project was successfully commissioned.
- Preventative maintenance was performed on the Malaysian cracking and leaching plant during the December shutdown.
- Construction of Stage 2 of the Mt Weld Expansion Project is progressing as planned, with completion expected by the end of FY25.
- A pathway has been identified to resolve wastewater management issues at the Seadrift site in the US.
Sentiment
Score: 5
Explanation: The report shows mixed results with increased sales revenue but lower than planned production and ongoing challenges. The company is making progress on expansion projects, but market conditions remain challenging.
Positives
- Sales revenue increased to $141.2 million, showing strong performance despite production challenges.
- The average selling price improved to $49.2/kg, indicating a positive trend in pricing.
- The Kalgoorlie facility was officially opened, marking a significant milestone.
- Stage 1 of the Mt Weld Expansion Project was successfully commissioned and integrated into operations.
- Preventative maintenance was completed on the Malaysian plant, which should improve future output.
- Technical solutions have been identified to address MREC impurity issues, avoiding future chemical treatment.
- A pathway has been identified to resolve wastewater management issues at the Seadrift site.
Negatives
- Total REO and NdPr production were lower than planned due to issues in December.
- The annual lanthanide processing limit in Malaysia was reached in late November, impacting production.
- Impurities in MREC feedstock caused production delays and required additional treatment.
- Market conditions remain challenging with low rare earth prices.
- The company experienced a kiln bearing failure in August 2024.
Risks
- Market conditions are expected to remain challenging with low rare earth prices into the March 2025 quarter.
- The company is still working to resolve wastewater management challenges at the Seadrift site.
- Production can be impacted by technical issues with new feedstocks, as seen with the MREC impurities.
- The company is dependent on the availability of chemical inputs for processing.
- The company is subject to annual processing limits in Malaysia.
Future Outlook
Market conditions are expected to remain challenging into the March 2025 quarter due to subdued demand in China and the extended lunar new year holiday period. Stage 2 of the Mt Weld Expansion Project is expected to be completed by the end of FY25.
Management Comments
- The company was delighted to welcome the Australian Minister for Resources and Northern Australia to officially open the new Kalgoorlie Facility.
- The commissioning and integration of Stage 1 of the Mt Weld Expansion Project are significant milestones for the Lynas 2025 growth plan.
- The sole focus on MREC processing in December has provided valuable learnings for the team.
- Technical solutions have been identified that will not require additional chemical treatment in the future.
Industry Context
The report highlights the challenges faced by rare earth producers due to low market prices and fluctuating demand, particularly in China. Lynas is focusing on strategic customers and optimizing product mix to mitigate these challenges. The company's expansion projects are aimed at increasing production capacity and reducing costs, which is a common strategy in the industry.
Comparison to Industry Standards
- The average selling price of $49.2/kg is a positive sign, but it is important to compare this to other rare earth producers to see if it is competitive.
- The production of 2,617 tonnes of total REO and 1,292 tonnes of NdPr is a significant volume, but it is important to compare this to other major producers such as China Northern Rare Earth Group and MP Materials.
- The company's focus on strategic customers and optimized product mix is a common strategy in the industry to maintain profitability during periods of low prices.
- The expansion projects at Mt Weld and Kalgoorlie are similar to other companies' efforts to increase production capacity and reduce costs.
- The issues with MREC impurities highlight the challenges of processing new feedstocks, which is a common issue in the industry.
Next Steps
- Implement technical solutions to address MREC impurity issues.
- Continue construction of Stage 2 of the Mt Weld Expansion Project.
- Progressively commission Stage 2 circuits.
- Commence energisation of the HV switchroom and commissioning of crushing circuit and bore water treatment plant.
- Continue to work with the Department of Defense to assess the pathway to resolve wastewater management challenges at the Seadrift site.
- Deliver solar panels to the Mt Weld site.
Key Dates
- August 2024: First ever failure of a kiln bearing in Malaysia.
- Late November 2024: Annual lanthanide processing limit reached in Malaysia.
- 8th November 2024: The Kalgoorlie Rare Earths Processing Facility was officially opened.
- 25th December 2024: Chemical inputs required for MREC treatment became available.
- 31 December 2024: End of the reporting quarter.
- March 2025: Market conditions expected to remain challenging.
- End of FY25: Expected completion of Stage 2 of the Mt Weld Expansion Project.
Keywords
Filings with Classifications
Production Update
- The successful first production of Terbium Oxide represents a significant expansion of Lynas' product capabilities and a positive operational milestone.
Results Presentation
- The company reports a profit in a challenging market, implying that the results were worse than expected.
Results Presentation
- NdPr production increased by 23% compared to 1H FY24.
- Sales revenue increased by 8% compared to 1H FY24.
Half Year Report
- The net profit after tax decreased significantly from $39.5 million to $5.9 million, indicating a worse financial performance compared to the previous year.
Interim Financial Report
- The results were worse than expected due to a significant decrease in net profit, driven by lower rare earth prices and increased production costs.
Quarterly Report
- The chemical inputs required for the treatment of MREC impurities were not available until December 25th, causing a delay in production.
Quarterly Report
- Production volumes were lower than planned due to issues with impurities in the MREC feedstock and the annual processing limit in Malaysia.
Annual General Meeting Presentation
- The significant increase in Mt Weld Mineral Resources and Ore Reserves, coupled with the successful completion of major projects and cost reductions, indicate results better than might have been expected.
Annual General Meeting Presentation
- Site works at the US facility are on hold due to a wastewater permitting issue.
Quarterly Report
- Rare earth prices remained low throughout most of Q1 FY25, resulting in lower than expected sales revenue compared to previous quarters.
Quarterly Report
- A permitting issue related to wastewater management has put a hold on earthworks for the U.S. Rare Earths Processing Facility.
ESG Report
- The net profit after tax was significantly lower than the previous year, indicating worse than expected financial performance.
Annual Report
- Earthworks for the planned U.S. Rare Earths Processing Facility have been delayed until a permitting issue related to wastewater management is resolved, which is unlikely to happen before the end of 2024.
Annual Report
- The net profit after tax decreased significantly from $310.7 million in FY23 to $84.5 million in FY24, primarily due to lower rare earth prices and reduced production volumes.
Company Presentation
- The company announced a 92% increase in Mineral Resources and a 63% increase in Mt Weld Ore Reserves.
Resource and Reserve Update
- The Mineral Resources and Ore Reserves have increased significantly compared to the 2018 estimates.
- The contained Dysprosium oxide in Ore Reserves has increased substantially.
- The updated Ore Reserve supports a longer mine life at expanded production rates.
Quarterly Report
- The company's REO and NdPr production were lower than the previous quarter.
Quarterly Report
- Completion of Stage 2 of the Mt Weld Expansion Project is now expected by the end of FY25.
- Delays in receiving concentrate due to disturbances to the global shipping industry and kiln maintenance shutdowns impacted downstream production.
Missing type for ID: 3288
- ASX:LYC announces a delay.
Investor Presentation
- Many new rare earth projects have stalled.
Investor Presentation
- Pricing at surprisingly low levels following strong production growth inside China.
Quarterly Report
- The commissioning timeline for the Kalgoorlie facility has been extended, leading to a budget increase.
Quarterly Report
- The Q3 FY24 revenue was significantly lower than the previous year due to lower NdPr prices and the decision to hold inventory.
Disclaimer: This summary was generated by artificial intelligence and its accuracy is not guaranteed. The information provided here is for general informational purposes only and does not constitute financial advice, recommendation, or endorsement of any kind. It may contain errors or omissions. You should not rely on this information to make financial decisions. Always seek the advice of a qualified financial professional before making any investment or financial decisions. Use of this information is at your own risk.