Quarterly Activities Report
Summary
- Lynas Rare Earths' Q1 FY25 sales revenue was A$120.5 million, and sales receipts were A$127.5 million.
- Total rare earth oxide (REO) production reached 2,722 tonnes, with NdPr production at 1,677 tonnes.
- The average NdPr market price was US$48/kg ex VAT during the quarter.
- Approximately 100 tonnes of NdPr remained at port at the end of the quarter.
- Closing cash and short-term deposits were A$414.3 million.
- Cash payments for CAPEX, exploration, and development totaled A$125.0 million.
- Progress on growth projects targeting 10.5kt NdPr capacity in FY25 is on track.
- Mt Weld expansion project Stage 1 (concentrate dewatering circuit) transitioned to operations.
- Mt Weld expansion project Stage 2 is forecast to be complete by the end of FY25.
- The Kalgoorlie Rare Earths Processing Facility ramp-up continues, focusing on stabilizing production and optimizing MREC quality and cost performance.
- A permitting issue related to wastewater management has delayed the U.S. Rare Earths Processing Facility earthworks.
Sentiment
Score: 5
Explanation: The report presents a mixed outlook. While progress on growth projects is positive, lower than expected rare earth prices and a permitting delay negatively impact the overall sentiment.
Positives
- Sales revenue of A$120.5 million in Q1 FY25.
- Progress on growth projects to reach 10.5kt NdPr capacity in FY25 remains on track.
- Mt Weld expansion project Stage 1 (concentrate dewatering circuit) is operational.
- Closing cash and short-term deposits of A$414.3 million.
- Low injury rates: 0.8 Lost Time Injury Rate and 4 Total Recordable Injury Rate per million hours worked.
Negatives
- Lower than expected rare earth prices during the quarter.
- Approximately 100 tonnes of NdPr remained at port at the end of the quarter.
- Permitting issue delaying the U.S. Rare Earths Processing Facility earthworks.
Risks
- Low rare earth prices impacting revenue.
- Permitting issues for the U.S. Rare Earths Processing Facility.
- Potential delays in the ramp-up of the Kalgoorlie facility.
Future Outlook
Progress on growth projects to deliver the target of 10.5kt NdPr capacity in FY25 is on track. Mt Weld expansion project Stage 2 is forecast to be complete by the end of FY25 and will be progressively commissioned.
Management Comments
- Rare Earths prices continued at low levels during Q1 FY25, with a small improvement in the NdPr price towards the end of the quarter.
- Production levels were managed in line with market demand.
- Progress on Lynas growth projects to deliver our target of 10.5kt NdPr capacity in FY25 continued on track.
Industry Context
The report highlights the impact of low rare earth prices on the industry, with Lynas managing production to align with market demand. The slight improvement in NdPr prices towards the end of the quarter may indicate a potential shift in market dynamics, but further observation is needed.
Next Steps
- Completion of Mt Weld expansion project Stage 2 by the end of FY25.
- Progressive commissioning of Mt Weld expansion project Stage 2.
- Continued ramp-up of the Kalgoorlie Rare Earths Processing Facility.
- Resolution of the permitting issue for the U.S. Rare Earths Processing Facility.
Key Dates
- 30 September 2024: End of the reporting period for Q1 FY25
- 30 October 2024: Date of the Quarterly Report release
- 27 November 2024: Date of the 2024 Annual General Meeting
Keywords
Filings with Classifications
Production Update
- The successful first production of Terbium Oxide represents a significant expansion of Lynas' product capabilities and a positive operational milestone.
Results Presentation
- The company reports a profit in a challenging market, implying that the results were worse than expected.
Half Year Report
- The net profit after tax decreased significantly from $39.5 million to $5.9 million, indicating a worse financial performance compared to the previous year.
Results Presentation
- NdPr production increased by 23% compared to 1H FY24.
- Sales revenue increased by 8% compared to 1H FY24.
Interim Financial Report
- The results were worse than expected due to a significant decrease in net profit, driven by lower rare earth prices and increased production costs.
Quarterly Report
- Production volumes were lower than planned due to issues with impurities in the MREC feedstock and the annual processing limit in Malaysia.
Quarterly Report
- The chemical inputs required for the treatment of MREC impurities were not available until December 25th, causing a delay in production.
Annual General Meeting Presentation
- The significant increase in Mt Weld Mineral Resources and Ore Reserves, coupled with the successful completion of major projects and cost reductions, indicate results better than might have been expected.
Annual General Meeting Presentation
- Site works at the US facility are on hold due to a wastewater permitting issue.
Quarterly Report
- Rare earth prices remained low throughout most of Q1 FY25, resulting in lower than expected sales revenue compared to previous quarters.
Quarterly Report
- A permitting issue related to wastewater management has put a hold on earthworks for the U.S. Rare Earths Processing Facility.
ESG Report
- The net profit after tax was significantly lower than the previous year, indicating worse than expected financial performance.
Annual Report
- The net profit after tax decreased significantly from $310.7 million in FY23 to $84.5 million in FY24, primarily due to lower rare earth prices and reduced production volumes.
Annual Report
- Earthworks for the planned U.S. Rare Earths Processing Facility have been delayed until a permitting issue related to wastewater management is resolved, which is unlikely to happen before the end of 2024.
Company Presentation
- The company announced a 92% increase in Mineral Resources and a 63% increase in Mt Weld Ore Reserves.
Resource and Reserve Update
- The Mineral Resources and Ore Reserves have increased significantly compared to the 2018 estimates.
- The contained Dysprosium oxide in Ore Reserves has increased substantially.
- The updated Ore Reserve supports a longer mine life at expanded production rates.
Quarterly Report
- Completion of Stage 2 of the Mt Weld Expansion Project is now expected by the end of FY25.
- Delays in receiving concentrate due to disturbances to the global shipping industry and kiln maintenance shutdowns impacted downstream production.
Quarterly Report
- The company's REO and NdPr production were lower than the previous quarter.
Missing type for ID: 3288
- ASX:LYC announces a delay.
Investor Presentation
- Many new rare earth projects have stalled.
Investor Presentation
- Pricing at surprisingly low levels following strong production growth inside China.
Quarterly Report
- The commissioning timeline for the Kalgoorlie facility has been extended, leading to a budget increase.
Quarterly Report
- The Q3 FY24 revenue was significantly lower than the previous year due to lower NdPr prices and the decision to hold inventory.
Disclaimer: This summary was generated by artificial intelligence and its accuracy is not guaranteed. The information provided here is for general informational purposes only and does not constitute financial advice, recommendation, or endorsement of any kind. It may contain errors or omissions. You should not rely on this information to make financial decisions. Always seek the advice of a qualified financial professional before making any investment or financial decisions. Use of this information is at your own risk.