STOCKMAN UPDATE - EXCELLENT METALLURGICAL TEST RESULTS
Summary
- Aeris Resources has completed metallurgical testwork on the Stockman Project, demonstrating improved metal recoveries using a modified flotation circuit and the Albion Process.
- The modified flotation circuit produces an export quality copper concentrate and a bulk concentrate containing copper, zinc, gold, and silver.
- Metal leaching of the bulk concentrate using the Albion Process indicates recoveries of over 98% for copper and zinc.
- Overall copper and zinc recoveries are now greater than 90%, with significantly improved gold recoveries.
- The company plans to proceed with detailed testwork and options engineering for a simplified ore treatment and Albion processing plants.
- The updated conceptual flotation flowsheet test results show a significant step-up in metal recovery compared to the original selective copper and zinc flotation flowsheet.
- The copper concentrate quality produced from the modified conceptual flotation flowsheet test results was 18% copper content, before any cleaning or optimisation of the flotation conditions.
Sentiment
Score: 8
Explanation: The document presents positive metallurgical testwork results that could significantly improve the economics of the Stockman Project. The focus on cost reduction and environmental impact is also favorable.
Highlights
- Metallurgical testwork validates the potential of the Albion Process to significantly enhance the Stockman Project's economics.
- The modified flotation circuit produces export quality copper concentrate and a bulk concentrate with copper, zinc, gold, and silver.
- Albion Process leaching of the bulk concentrate shows recoveries of +98% for copper and zinc.
- Overall copper and zinc recoveries now exceed 90%, with improved gold recoveries.
- The company will proceed with detailed testwork and options engineering for simplified ore treatment and Albion processing plants.
- The engineering study has recommended conceptual level flowsheets, equipment sizes and reagent consumption rates for the Albion Process plant.
- The first selective flotation of the copper circuit achieved an estimated recovery of 41% at 21% Cu to a copper-only concentrate for export and smelting.
- The bulk flotation circuit achieved a copper and zinc recovery to a bulk concentrate of 51% and 95% respectively.
Positives
- Improved metal recoveries lead to increased revenue.
- Simplified ore processing plant design reduces the physical footprint, lowering capital and operating costs.
- Reduced carbon emissions due to lower energy consumption.
- The fast kinetics of the leaching of the Stockman bulk concentrate allows for a modest size plant.
- The modified conceptual flotation flowsheet test results show a significant step-up in metal recovery compared to the original selective copper and zinc flotation flowsheet.
- The copper concentrate quality produced from the modified conceptual flotation flowsheet test results was 18% copper content, before any cleaning or optimisation of the flotation conditions.
Negatives
- Silver extraction rates were lower at 3% 36% and may require a lime boil pre-treatment process.
Risks
- Further investigation is needed to determine the optimum precipitation chemistry and marketing terms for intermediate products.
- The company needs to improve silver and gold recovery and saleable product pathways.
- Ore variability testing is required.
Future Outlook
An ASX update on the concept engineering study results should be available in the next quarter.
Management Comments
- Aeris Executive Chairman, Andre Labuschagne said These latest metallurgical testwork results validate our view that the Albion Process has the potential to significantly enhance the overall economics of the Stockman Project.
Industry Context
The use of Albion Process for refractory ores is becoming more common in the mining industry to improve metal recoveries from complex ore bodies. This approach can potentially make previously uneconomic deposits viable.
Comparison to Industry Standards
- The Albion Process is a known technology developed by Glencore Technology and used in several operations globally.
- Other companies using similar leaching technologies for complex base metal ores include companies like Nyrstar and Trevali Mining.
- The reported copper and zinc recoveries of >90% are competitive with other Albion Process operations.
Stakeholder Impact
- Shareholders: Potential for increased project value and returns.
- Employees: Possible job creation related to the project development.
- Customers: Potential for a reliable supply of copper and zinc concentrates.
- Community: Reduced environmental impact due to a smaller plant footprint.
- Suppliers: Opportunities for supplying reagents and equipment to the project.
Next Steps
- Complete concept engineering studies for both the flotation plant and Albion Process plant design.
- Select intermediate copper and zinc products and marketing payability estimates; test further product refinement paths and value.
- Improve silver and gold recovery and saleable product pathways.
- Conduct ore variability testing.
- Explore potential economic recovery of sulphur through the production of elemental sulphur or sulphuric acid.
Key Dates
- 1970s: Stockman area identified as prospective for base metals by WMC.
- 1977: Wilga deposit discovered in drilling by a WMC/BP Minerals JV.
- 1979: Currawong deposit discovered by drilling.
- 1998: Denehurst went into receivership.
- 2023: Diamond drilling program provided new drill core for metallurgy testing purposes.
- 04 July 2024: ASX/Media Release Date
Keywords
Filings with Classifications
Market Announcement
- The announcement concerns a capital raising by Aeris Resources Limited.
Quarterly Report
- Underground ore production was impacted by delays to stope filling at Budgerygar due to a failure of the newly commissioned paste pump.
- Ramp up to full production at Murrawombie Pit was slower than expected due to the contractor having difficulty securing skilled operators.
Mineral Resource Update
- The document contains better than expected results due to the significant increase in copper and gold resources at the Constellation deposit, with a substantial upgrade to the Indicated Mineral Resource.
Half-Year Results
- The company's financial results for HY25 are significantly better than HY24, with increased revenue, lower costs, and a substantial improvement in profitability.
Quarterly Report
- The ANZ facility was renewed to July 2025 to facilitate the refinancing process.
- The company is working to complete refinancing.
Quarterly Report
- There were delays to the paste fill plant at Budgerygar.
Quarterly Report
- The new paste fill pump and reticulation system at the Budgerygar mine was delayed due to overseas supplier issues.
Annual General Meeting Results
- The AGM approved the issuance of an additional 10% of the issued capital over a 12-month period.
Facility Extension Announcement
- The refinancing process implies the company is seeking additional capital, though the specific method is not detailed.
Quarterly Report
- Tritton and Cracow exceeded production expectations, resulting in better than expected overall production.
- The AISC was lower than expected, indicating better cost management.
Quarterly Operational Report
- The completion of mining activities at Mt Colin is now expected in late November 2024.
Quarterly Operational Report
- Copper equivalent production exceeded expectations, reaching 10.2kt for the quarter.
- All-in sustaining costs (AISC) were lower than anticipated at A$5.32/lb.
Annual Report
- Despite lower overall revenue, Aeris Resources significantly exceeded expectations for Adjusted EBITDA, demonstrating improved operational efficiency and benefiting from higher commodity prices.
Annual General Meeting Notice
- Resolution 3 proposes issuing up to an additional 10% of the issued capital over a 12-month period.
- Funds raised would be used for exploration, assessing investment opportunities, and working capital.
Company Presentation
- Mt Colin's copper production was below guidance due to limited toll processing availability, indicating a delay in processing mined ore.
Quarterly Activities Report
- Mining activities at Mt Colin are now expected to continue until early Q2 FY25, which is later than the previously expected late Q4 FY24.
Presentation
- Delays in toll processing for Mt Colin have resulted in a significant buildup of ore stockpiles.
Missing type for ID: 3564
- ASX:AIS announces worse than expected results.
Missing type for ID: 3564
- ASX:AIS announces better than expected results.
Metallurgical Testwork Results
- The metal recoveries are better than the original conventional flotation flowsheet.
Exploration Update
- The DHEM results suggest that the targeted copper lodes are deeper than initially anticipated, which could increase exploration costs and delay potential production.
Group Mineral Resource and Ore Reserve Statement
- The Jaguar Ore Reserve has not been updated since the previous reporting period (end December 2022).
Group Mineral Resource and Ore Reserve Statement
- The document contains worse than expected results due to the overall decrease in Group Ore Reserve tonnage.
Exploration Update
- The new IP anomaly is larger than the one associated with the existing Canbelego Main Lode, suggesting the potential for a larger copper deposit.
Quarterly Report
- Tritton's metal production was impacted by labour and equipment availability, leading to lower than expected output.
Quarterly Activities Report
- Mt Colin toll processing and copper production are behind schedule.
- Due to reduced processing runs through the year, copper production is forecast to be below guidance for FY24 at Mt Colin.
Exploration Update
- The document contains better than expected results because new geophysical surveys have identified significant new copper targets in close proximity to known, high-grade copper mineralisation at the Canbelego deposit.
Disclaimer: This summary was generated by artificial intelligence and its accuracy is not guaranteed. The information provided here is for general informational purposes only and does not constitute financial advice, recommendation, or endorsement of any kind. It may contain errors or omissions. You should not rely on this information to make financial decisions. Always seek the advice of a qualified financial professional before making any investment or financial decisions. Use of this information is at your own risk.