ASX
150 days, 15 hours ago 
AIS
Aeris Resources Limited
Notification of cessation of securities - AIS
Aeris Resources Limited announced the cessation of 2,319,743 performance rights due to employee resignations and unmet performance conditions.

ASX
150 days, 16 hours ago 
AIS
Aeris Resources Limited
Application for quotation of securities - AIS
Aeris Resources Limited (AIS) is applying for quotation of 769,959 ordinary shares following the conversion of performance rights.

ASX
160 days, 2 hours ago 
AIS
Aeris Resources Limited
SENIOR MANAGEMENT UPDATE
Aeris Resources Limited announces the appointment of a new Chief Technical Officer and Chief People Officer, replacing a retiring CTO and promoting from within.

ASX
165 days, 18 hours ago 
AIS
Aeris Resources Limited
RESULTS OF AGM
Aeris Resources Limited's 2024 Annual General Meeting saw all resolutions pass, including the re-election of a director and approval to issue an additional 10% of issued capital over 12 months.
Capital raise
 

ASX
165 days, 23 hours ago 
AIS
Aeris Resources Limited
2024 AGM PRESENTATION
Aeris Resources Limited presented its Annual General Meeting on November 27, 2024, outlining its FY25 production guidance of 40-48kt copper equivalent, driven by diversified operations and significant internal growth opportunities.

ASX
178 days, 16 hours ago 
AIS
Aeris Resources Limited
EXTENSION OF ANZ FACILITY
Aeris Resources Limited announces an extension of its ANZ facility maturity date to January 31, 2025, providing additional time to complete the refinancing process.
Capital raise
 

ASX
188 days, 18 hours ago 
AIS
Aeris Resources Limited
UPDATED SEPTEMBER QUARTERLY REPORT PRESENTATION
Aeris Resources Limited (ASX:AIS) released an updated September quarterly report presentation, clarifying cross-references to exploration results, mineral resources, and ore reserves, without materially altering the original content.

ASX
194 days, 1 hours ago 
AIS
Aeris Resources Limited
SEPTEMBER QUARTERLY REPORT PRESENTATION
Aeris Resources reported strong Q1 FY25 results, exceeding production targets at Tritton and Cracow, while Mt Colin underperformed due to processing challenges, and Jaguar remains on care and maintenance.
Better than expected
 

ASX
194 days, 1 hours ago 
AIS
Aeris Resources Limited
QUARTERLY ACTIVITIES REPORT - SEPT 2024
Aeris Resources reported strong operational results for the September 2024 quarter, with improved copper equivalent production and all-in sustaining costs, but noted challenges at Mt Colin and the ongoing care and maintenance of Jaguar operations.
Better than expected
 
Delay expected
 

ASX
198 days, 21 hours ago 
AIS
Aeris Resources Limited
ANNUAL REPORT 30 JUNE 2024
Aeris Resources reported a significant increase in Adjusted EBITDA to $107.0 million in FY24, driven by improved production and higher commodity prices, despite lower revenue and challenges at some operations.
Better than expected
 

ASX
198 days, 21 hours ago 
AIS
Aeris Resources Limited
NOTICE OF ANNUAL GENERAL MEETING/PROXY FORM
Aeris Resources Limited (ASX: AIS) has announced its Annual General Meeting (AGM) will be held on November 27, 2024, to consider resolutions including the adoption of the remuneration report, director re-election, and a capital increase.
Capital raise
 

ASX
208 days, 22 hours ago 
AIS
Aeris Resources Limited
EXTENSION OF ANZ FACILITY
Aeris Resources Limited announces an extension of its ANZ facility maturity date to November 15, 2024, providing additional time to complete the refinancing process.

ASX
277 days, 20 hours ago 
AIS
Aeris Resources Limited
CORRECTION - DIGGERS AND DEALERS PRESENTATION
Aeris Resources Limited releases a corrected version of its Diggers and Dealers presentation, addressing JORC compliance and providing updated information on mineral resources and ore reserves.

ASX
279 days, 16 hours ago 
AIS
Aeris Resources Limited
AERIS RESOURCES - DIGGERS AND DEALERS PRESENTATION
Aeris Resources, an Australian mid-tier base and precious metals producer, highlights its diversified production, growth opportunities, and strategic assets in a presentation at Diggers and Dealers in August 2024.

ASX
283 days, 0 hours ago 
AIS
Aeris Resources Limited
INTERIM - ORGANISATIONAL CHANGES
Aeris Resources Limited announces interim organizational changes as CFO Rob Brainsbury temporarily steps back due to personal reasons, with Dane Van Heerden assuming the role of Acting-CFO.

ASX
285 days, 20 hours ago 
AIS
Aeris Resources Limited
JUNE QUARTERLY REPORT PRESENTATION
Aeris Resources reports Q4 FY24 results, achieving production and cost guidance for FY24 at the group level, Tritton, and Cracow, while Mt Colin's production fell short due to toll processing availability.
Delay expected
 

ASX
286 days, 0 hours ago 
AIS
Aeris Resources Limited
FY25 GUIDANCE
Aeris Resources Limited forecasts group copper equivalent production of 40-48kt and Cracow gold production of 40-49koz for FY25, with increased growth capital investment at Tritton.

ASX
286 days, 0 hours ago 
AIS
Aeris Resources Limited
QUARTERLY ACTIVITIES REPORT - JUNE 2024
Aeris Resources reports copper equivalent production of 10.2kt for the quarter ended June 30, 2024, with production and cost guidance achieved for FY24 at the group level and at Tritton and Cracow.
Delay expected
 

ASX
286 days, 17 hours ago 
AIS
Aeris Resources Limited
INVESTOR CONFERENCE CALL DETAILS - 30 JULY 2024
Aeris Resources Limited (ASX: AIS) will release its June Quarterly Activities Report on July 30, 2024, followed by a webinar presentation hosted by Executive Chairman Andre Labuschagne to discuss the results.

ASX
297 days, 21 hours ago 
AIS
Aeris Resources Limited
INVESTOR PRESENTATION - NOOSA MINING INVESTOR CONFERENCE
Aeris Resources, an Australian mid-tier base and precious metals producer, highlights diversified production, growth opportunities, and a strategic focus on copper during its Noosa Mining Conference presentation in July 2024.
Delay expected
 

ASX
305 days, 0 hours ago 
AIS
Aeris Resources Limited
FY24 PRODUCTION GUIDANCE UPDATE
Aeris Resources Limited (ASX: AIS) exceeded FY24 production guidance for Tritton (copper), Cracow (gold), and Jaguar (zinc), while Mt Colin copper production fell short due to processing constraints, though ore production exceeded expectations.
Better than expected
 
Worse than expected
 

ASX
312 days, 0 hours ago 
AIS
Aeris Resources Limited
STOCKMAN UPDATE - EXCELLENT METALLURGICAL TEST RESULTS
Aeris Resources' Stockman Project shows potential for significantly improved returns through modified flotation and Albion Process testwork, leading to higher metal recoveries.
Better than expected
 

ASX
313 days, 1 hours ago 
AIS
Aeris Resources Limited
HLX: Canbelego Downhole Geophysics Update
Helix Resources' downhole geophysics at Canbelego indicates potential copper lodes lie deeper than initially anticipated, shifting focus to the Bijoux copper anomaly.
Worse than expected
 

ASX
325 days, 22 hours ago 
AIS
Aeris Resources Limited
RESULTS OF EGM
Aeris Resources Limited shareholders approved the resolution for ratification of prior issue of placement shares at the Extraordinary General Meeting.

ASX
329 days, 0 hours ago 
AIS
Aeris Resources Limited
EXPLORATION AND RESOURCE DRILLING UPDATE
Aeris Resources is focusing on resource definition and exploration programs at its Tritton, Cracow, and Jaguar operations, aiming to increase mineral resources and discover new gold corridors.

ASX
329 days, 0 hours ago 
AIS
Aeris Resources Limited
GROUP MINERAL RESOURCE AND ORE RESERVE STATEMENT
Aeris Resources Limited reports a slight decrease in Group Mineral Resource tonnage and a decrease in Group Ore Reserve tonnage primarily due to mining depletion as of December 31, 2023.
Worse than expected
 
Delay expected
 

ASX
334 days, 1 hours ago 
AIS
Aeris Resources Limited
HLX: Canbelego Copper Drilling Intersects Mineralised Fault
Helix Resources intersects a mineralized fault zone at its Canbelego copper project, indicating potential for new copper lodes, but further geophysical modeling is needed to assess the significance of the discovery.

ASX
335 days, 1 hours ago 
AIS
Aeris Resources Limited
SENIOR MANAGEMENT CHANGES
Aeris Resources Limited announces senior management changes, including the appointment of a new Chief Operating Officer and a Chief Technology Officer, effective immediately.

ASX
360 days, 0 hours ago 
AIS
Aeris Resources Limited
NOTICE OF EXTRAORDINARY GENERAL MEETING
Aeris Resources Limited (ASX:AIS) is holding an Extraordinary General Meeting (EGM) on June 20, 2024, to seek shareholder ratification for a prior issue of placement shares.

ASX
361 days, 1 hours ago 
AIS
Aeris Resources Limited
HLX: Canbelego Copper Drilling Starts
Helix Resources commences drilling at the Canbelego Copper Project to test a high-priority geophysics anomaly, with initial assay results expected in late June.

ASX
369 days, 1 hours ago 
AIS
Aeris Resources Limited
HLX:New IP ExtendsTarget Zone For New Copper Lodes-Canbelego
Helix Resources identifies a significant new copper target zone at Canbelego, larger than the existing Main Lode, and plans to commence drilling this month.
Better than expected
 

ASX
377 days, 0 hours ago 
AIS
Aeris Resources Limited
MARCH QUARTERLY REPORT PRESENTATION
Aeris Resources reports Q3 FY24 results with copper equivalent production of 9.1kt, impacted by labour and equipment availability at Tritton, while maintaining FY24 guidance.
Worse than expected
 

ASX
377 days, 1 hours ago 
AIS
Aeris Resources Limited
QUARTERLY ACTIVITIES REPORT - MARCH 2024
Aeris Resources reports copper equivalent production of 9.1kt for the quarter ended March 31, 2024, with maintained FY24 guidance despite some operational challenges.
Delay expected
 

ASX
377 days, 22 hours ago 
AIS
Aeris Resources Limited
INVESTOR CONFERENCE CALL DETAILS - 30 APRIL 2024
Aeris Resources Limited will release its March 2024 Quarterly Activities Report on April 30, 2024, followed by an investor webinar hosted by Executive Chairman Andre Labuschagne.

ASX
398 days, 1 hours ago 
AIS
Aeris Resources Limited
HLX: Canbelego Copper Resource Growth Potential Expanded
Helix Resources identifies new copper targets at Canbelego and Caballero through successful IP geophysics surveys, paving the way for expanded drilling and resource growth.
Better than expected
 

AIS 
Aeris Resources Limited 
ASX

QUARTERLY ACTIVITIES REPORT - MARCH 2024

Sentiment:
 Quarterly Activities Report
 29 April 2024 7:04 PM

Aeris Resources reports copper equivalent production of 9.1kt for the quarter ended March 31, 2024, with maintained FY24 guidance despite some operational challenges.

Delay expected
  Mt Colin toll processing and copper production are behind schedule.  Due to reduced processing runs through the year, copper production is forecast to be below guidance for FY24 at Mt Colin. 

Summary
  • Aeris Resources Limited reported a copper equivalent production of 9.1kt for the quarter ended March 31, 2024, at an AISC of A$5.31/lb.
  • Tritton's production was impacted by labour and equipment availability, but contract labour and additional equipment have been introduced to improve production rates next quarter.
  • Cracow's gold production and costs were in line with the plan, with recent drilling identifying potential new vein structures in the Western Vein Field.
  • Mt Colin mine production was in line with the plan, although toll processing and copper production were behind schedule.
  • Jaguar is on care and maintenance, with exploration focusing on gold potential while a prefeasibility study is underway.
  • Stockman feasibility work on the Albion process continues.
  • The Environmental Amendment for underground mining at Barbara has been submitted, and a feasibility study has commenced.
  • Group FY24 guidance is maintained, with more information on forecast production and costs provided in the operational summaries.
  • The company had useable cash and receivables of $28.3 million at the end of the quarter, with a closing cash balance of $19.4 million.
Sentiment

Score: 6

Explanation: The report presents a mixed picture, with some positive aspects like gold production at Cracow and cost control, but also challenges such as production issues at Tritton and delays at Mt Colin. The maintained guidance provides some reassurance, but the overall sentiment is neutral to slightly positive.

Highlights
  • Copper equivalent production reached 9.1kt for the quarter at an AISC of A$5.31/lb.
  • Gold production at Cracow is in line with the plan, with potential new vein structures identified.
  • Mt Colin mine production is in line with the plan, though toll processing is behind schedule.
  • Aeris has recorded no lost time injuries through the last quarter, bringing the 12-month LTIFR down to 1.10.
  • Tritton expects to deliver copper production around the mid-point of the FY24 guidance range.
  • Cracow is on track to achieve the upper end of production guidance and the lower end of operating and capital cost guidance for FY24.
  • Mining at Mt Colin will continue approximately 3 months longer than planned and into Q1 FY25 due to strong geotechnical performance.
  • At the end of FY24, ore stockpiles of approximately 200kt grading 2% Cu available for processing are forecast at Mt Colin.
  • Exploration at the Jaguar Operation has transitioned to focusing exclusively on gold.
  • At the end of the quarter, Aeris had useable cash and receivables of $28.3 million with a closing cash balance of $19.4 million.
Positives
  • Copper equivalent production of 9.1kt for the quarter.
  • AISC of A$5.31/lb for copper equivalent production.
  • Gold production and costs at Cracow are in line with the plan.
  • Potential new vein structures identified at Cracow.
  • Mt Colin mine production is in line with the plan.
  • Mining at Mt Colin will continue approximately 3 months longer than planned and into Q1 FY25 due to strong geotechnical performance.
  • Operating costs for the quarter were in line with plan at Cracow.
  • Exploration at the Jaguar Operation has transitioned to focusing exclusively on gold.
  • Aeris has recorded no lost time injuries through the last quarter, bringing the 12-month LTIFR down to 1.10.
Negatives
  • Tritton production was impacted by labour and equipment availability.
  • Mt Colin toll processing and copper production are behind schedule.
  • Tritton's AISC (unit costs) for Q3 were higher quarter-on-quarter on the back of lower production volumes.
  • Due to reduced processing runs through the year, copper production is forecast to be below guidance for FY24 at Mt Colin.
Risks
  • Labour and equipment availability issues at Tritton could continue to impact production.
  • Delays in toll processing at Mt Colin could affect copper production.
  • Lower mined grades at Cracow could impact recovery rates.
  • Fluctuations in commodity prices could affect revenue and profitability.
  • The success of exploration activities at Jaguar is uncertain.
  • The feasibility studies for Stockman and Barbara may not yield positive results.
Future Outlook

Aeris expects Tritton to deliver copper production around the mid-point of the FY24 guidance range, and Cracow is on track to achieve the upper end of production guidance and lower end of operating and capital cost guidance for FY24.

Industry Context

This report reflects the ongoing challenges and opportunities in the mining sector, with a focus on maintaining production levels while managing costs and exploring new growth opportunities. The company's focus on exploration and feasibility studies aligns with industry trends towards securing future resources.

Comparison to Industry Standards
  • AISC of A$5.31/lb is competative with other Australian copper miners.
  • Gold production of 10.2koz at AISC of A$2,679/oz is competative with other Australian gold miners.
Stakeholder Impact
  • Shareholders: Maintained guidance provides some stability, but production issues at Tritton and delays at Mt Colin could be concerning.
  • Employees: Operational changes at Tritton and Jaguar could impact job security.
  • Customers: Potential delays in copper production at Mt Colin could affect supply.
  • Suppliers: Changes in mining plans could affect demand for goods and services.
  • Creditors: Refinancing of debt and bonding facilities is underway.
Next Steps
  • Implement measures to improve production rates at Tritton.
  • Continue exploration drilling at Cracow.
  • Complete the Barbara feasibility study.
  • Commence drilling at the Heather Bore prospect at Jaguar.
  • Finalize Albion leach test work for Stockman in Q4 FY2024.
  • Schedule processing runs for Mt Colin ore stockpiles in Q1 and Q2 of FY25.
Key Dates
  • July 2022: Previously unreported drill hole completed in July 2022
  • 31 March 2024: End of the reported quarter.
  • Early May 2024: The next drilling program at Constellation is scheduled to commence.
  • Mid-April: A processing run for ca. 105kt ore was completed at Mt Colin.
  • June quarter: Drilling will commence at the Heather Bore prospect at Jaguar.
  • Q1 2025: Mining at Mt Colin will continue approximately 3 months longer than planned and into Q1 FY25.
  • Q1 2025: The Feasibility Study for the Barbara underground mining project is expected to be completed.
Keywords

AIS 
Aeris Resources Limited 
ASX
Sector: Materials
 
Filings with Classifications
Capital raise
7 May 2025 7:31 PM

Market Announcement
  • The announcement concerns a capital raising by Aeris Resources Limited.
Delay expected
27 April 2025 7:52 PM

Quarterly Report
  • Underground ore production was impacted by delays to stope filling at Budgerygar due to a failure of the newly commissioned paste pump.
  • Ramp up to full production at Murrawombie Pit was slower than expected due to the contractor having difficulty securing skilled operators.
Better than expected
30 March 2025 7:12 PM

Mineral Resource Update
  • The document contains better than expected results due to the significant increase in copper and gold resources at the Constellation deposit, with a substantial upgrade to the Indicated Mineral Resource.
Better than expected
26 February 2025 5:48 PM

Half-Year Results
  • The company's financial results for HY25 are significantly better than HY24, with increased revenue, lower costs, and a substantial improvement in profitability.
Capital raise
2 February 2025 7:45 PM

Quarterly Report
  • The ANZ facility was renewed to July 2025 to facilitate the refinancing process.
  • The company is working to complete refinancing.
Delay expected
2 February 2025 7:45 PM

Quarterly Report
  • There were delays to the paste fill plant at Budgerygar.
Delay expected
30 January 2025 6:03 PM

Quarterly Report
  • The new paste fill pump and reticulation system at the Budgerygar mine was delayed due to overseas supplier issues.
Capital raise
27 November 2024 12:21 AM

Annual General Meeting Results
  • The AGM approved the issuance of an additional 10% of the issued capital over a 12-month period.
Capital raise
14 November 2024 2:57 AM

Facility Extension Announcement
  • The refinancing process implies the company is seeking additional capital, though the specific method is not detailed.
Better than expected
29 October 2024 6:34 PM

Quarterly Report
  • Tritton and Cracow exceeded production expectations, resulting in better than expected overall production.
  • The AISC was lower than expected, indicating better cost management.
Delay expected
29 October 2024 6:23 PM

Quarterly Operational Report
  • The completion of mining activities at Mt Colin is now expected in late November 2024.
Better than expected
29 October 2024 6:23 PM

Quarterly Operational Report
  • Copper equivalent production exceeded expectations, reaching 10.2kt for the quarter.
  • All-in sustaining costs (AISC) were lower than anticipated at A$5.32/lb.
Better than expected
24 October 2024 10:55 PM

Annual Report
  • Despite lower overall revenue, Aeris Resources significantly exceeded expectations for Adjusted EBITDA, demonstrating improved operational efficiency and benefiting from higher commodity prices.
Capital raise
24 October 2024 10:52 PM

Annual General Meeting Notice
  • Resolution 3 proposes issuing up to an additional 10% of the issued capital over a 12-month period.
  • Funds raised would be used for exploration, assessing investment opportunities, and working capital.
Delay expected
29 July 2024 11:29 PM

Company Presentation
  • Mt Colin's copper production was below guidance due to limited toll processing availability, indicating a delay in processing mined ore.
Delay expected
29 July 2024 7:52 PM

Quarterly Activities Report
  • Mining activities at Mt Colin are now expected to continue until early Q2 FY25, which is later than the previously expected late Q4 FY24.
Delay expected
17 July 2024 11:02 PM

Presentation
  • Delays in toll processing for Mt Colin have resulted in a significant buildup of ore stockpiles.
Worse than expected
10 July 2024 7:20 PM

Missing type for ID: 3564
  • ASX:AIS announces worse than expected results.
Better than expected
10 July 2024 7:20 PM

Missing type for ID: 3564
  • ASX:AIS announces better than expected results.
Better than expected
3 July 2024 7:39 PM

Metallurgical Testwork Results
  • The metal recoveries are better than the original conventional flotation flowsheet.
Worse than expected
2 July 2024 6:21 PM

Exploration Update
  • The DHEM results suggest that the targeted copper lodes are deeper than initially anticipated, which could increase exploration costs and delay potential production.
Delay expected
16 June 2024 7:22 PM

Group Mineral Resource and Ore Reserve Statement
  • The Jaguar Ore Reserve has not been updated since the previous reporting period (end December 2022).
Worse than expected
16 June 2024 7:22 PM

Group Mineral Resource and Ore Reserve Statement
  • The document contains worse than expected results due to the overall decrease in Group Ore Reserve tonnage.
Better than expected
7 May 2024 6:22 PM

Exploration Update
  • The new IP anomaly is larger than the one associated with the existing Canbelego Main Lode, suggesting the potential for a larger copper deposit.
Worse than expected
29 April 2024 8:01 PM

Quarterly Report
  • Tritton's metal production was impacted by labour and equipment availability, leading to lower than expected output.
Delay expected
29 April 2024 7:04 PM

Quarterly Activities Report
  • Mt Colin toll processing and copper production are behind schedule.
  • Due to reduced processing runs through the year, copper production is forecast to be below guidance for FY24 at Mt Colin.
Better than expected
8 April 2024 7:05 PM

Exploration Update
  • The document contains better than expected results because new geophysical surveys have identified significant new copper targets in close proximity to known, high-grade copper mineralisation at the Canbelego deposit.

Disclaimer: This summary was generated by artificial intelligence and its accuracy is not guaranteed. The information provided here is for general informational purposes only and does not constitute financial advice, recommendation, or endorsement of any kind. It may contain errors or omissions. You should not rely on this information to make financial decisions. Always seek the advice of a qualified financial professional before making any investment or financial decisions. Use of this information is at your own risk.