Critical Minerals Conference Presentation
Summary
- Arafura Rare Earths presented at the 2024 Australian Critical Minerals Conference.
- The presentation focused on the Nolans Project and its strategic importance.
- The company highlighted that the project is construction-ready, pending funding completion.
- Arafura is targeting the second half of CY24 for construction commencement.
- The presentation addressed the structural deficit in the NdPr market, emphasizing the need for new supply sources.
- The company noted that the Nolans Project is one of the most advanced ore-to-oxide development projects globally.
- Arafura is targeting 80% of planned production as binding offtake, with 56% already secured and discussions ongoing to reach 185% of the target.
- The company is actively engaging with potential equity partners and has secured conditional approvals for debt facilities.
- Arafura has a refreshed leadership team and board.
- The company is focused on ESG principles and their integration into the business.
Sentiment
Score: 7
Explanation: The presentation is generally positive, highlighting the project's progress, strategic importance, and market opportunity. However, the reliance on securing funding and government approvals introduces some uncertainty.
Positives
- The Nolans Project is construction-ready, pending funding.
- The project has secured significant offtake agreements, exceeding the initial target.
- Arafura has conditional approvals for a substantial portion of its debt financing.
- The company has a strong focus on ESG principles.
- The Nolans Project is located in a tier 1 jurisdiction.
- The project has access to existing infrastructure.
- The company has a large, high-grade resource.
Negatives
- The project is still contingent on securing full funding.
- The company is awaiting approval of relevant management plans in support of Commonwealth Government approvals already received.
- The company has a cash balance of A$58m as of March 31, 2024, which may require additional funding to reach production.
Risks
- The project's timeline is dependent on securing the remaining debt and equity financing.
- Delays in government approvals could impact the construction timeline.
- Fluctuations in NdPr prices could affect the project's economics.
- The company is targeting commercial bank lending under ECA covered tranches supported by untied loan guarantees from Euler Hermes and KEXIM, which may not be secured.
- The company is targeting 80% of planned production as binding offtake, but there is no guarantee that the company will reach its desired production levels at Nolans in full or at all.
Future Outlook
Arafura is focused on commencing construction in the second half of CY24, subject to funding, and is targeting NdPr users not aligned with Made in China 2025 strategy.
Industry Context
The presentation highlights the growing demand for NdPr driven by the electric vehicle and wind turbine industries, and the need for diversified supply chains outside of China. The Nolans Project is positioned as a key ex-China supply source.
Comparison to Industry Standards
- The presentation benchmarks Arafura's Nolans Project against Lynas' Mount Weld and MP Materials' Mountain Pass, highlighting its large, high-grade resource.
- Lynas is currently producing 12.00 tonnes of NdPr Oxide.
- MP Materials is currently producing 6.00 tonnes of NdPr Oxide.
- Arafura is targeting 4.44 tonnes of NdPr Oxide.
Stakeholder Impact
- Shareholders: Potential for increased value if the project achieves production and benefits from the NdPr market growth.
- Employees: Job creation during construction and operation phases.
- Customers: Access to a secure and diversified supply of NdPr.
- Suppliers: Opportunities to provide goods and services to the project.
- Creditors: Potential returns on debt financing.
Next Steps
- Finalize debt financing facilities.
- Secure equity funding.
- Commence construction in the second half of CY24.
- Continue offtake discussions to secure additional agreements.
Key Dates
- 7 June 2017: Date of ASX announcement regarding Detailed Resource Assessment Completed
- 16 March 2020: Date of ASX announcement regarding Major Increase in Mine Life for the Nolans Project
- 11 May 2021: Referenced ASX Announcement date for planned production of 4,440tpa
- 11 November 2022: Date of ASX announcement related to capital cost of A$1,590 million
- 29 March 2023: Date of ASX announcement regarding ECA covered tranches
- 20 June 2023: Date of ASX announcement regarding ECA covered tranches
- 7 March 2023: Referenced Lynas ASX announcement date regarding JARE extending support for Lynas growth plan
- 12 October 2023: Referenced Lynas ASX announcement date regarding Annual Report FY2023
- November 2023: Referenced Macquarie Rare Earths Update A delicate balance for NdPr
- 21 March 2024: Referenced S&P Global Market Intelligence report regarding average global mine lead times
- 22 March 2024: Date used for enterprise value calculation in peer benchmarking
- 1 May 2024: Date for market cap data
- 27 May 2024: Estimated average value of ~$50 for NdPr
- 29 May 2024: Date of the presentation at the Australian Critical Minerals Conference
- CY24 Q4: Target for sufficient liquidity
- CY24 2H: Targeting commencement of construction
Keywords
Filings with Classifications
Conference Presentation
- The sources and uses of funds section includes an increase in ramp-up period from 2 years to 3 years and a 3-month delay in first production.
Conference Presentation
- The company requires a new equity requirement of US$793m (including COF).
- Less NRFC US$133m (A$200m).
- Remaining new equity requirement of US$660m.
Quarterly Activities Report and Appendix 5B
- The final investment decision for Nolans has the potential to extend beyond the previously advised window of the first half of 2025 calendar year due to the assessment of a potential joint venture structure.
Quarterly Activities Report and Appendix 5B
- Arafura is assessing a potential joint venture (JV) structure which could significantly reduce the equity required to fund Arafura's remaining project interest.
- The company and its advisors regularly consider and assess options put forward by third parties (including potential corporate and project-level transactions) which could, if implemented, give rise to an alternative pathway to the funding and development of the Project for the benefit of shareholders.
Investor Presentation
- The company plans to raise equity through industry cornerstones, institutional investors, and an offer to new and existing shareholders.
- The equity raise is intended to fund the US$1.2 billion Nolans Project.
Interim Financial Report
- Arafura signed a binding term sheet with the NRFC for a A$200 million investment through unsecured convertible notes.
- The company may seek additional equity to reduce the amount of funding being sought through public raising.
Interim Financial Report
- The net loss decreased compared to the previous year (A$18.85 million vs A$66.87 million).
Update to Agreement
- The gas supply agreement deadline has been extended from February 4, 2025, to March 31, 2025.
Quarterly Activities Report
- The company is engaging with other potential cornerstone investors to secure the remaining equity required for the project.
- The A$200 million investment from the NRFC is expected to be a catalyst for attracting additional equity funding.
Quarterly Activities Report
- The gas supply agreement condition precedent date has been extended to 4 February 2025, with potential for further extension.
Funding Announcement
- The convertible notes will convert into shares at a 40% premium to the reference price, which will be determined by a future equity raising.
- The company expects to announce the equity financing around the time of the Final Investment Decision for the Nolans Project.
Project Update
- The condition precedent date for the gas supply agreement has been extended from December 31, 2024, to February 4, 2025.
Operational Update
- The condition precedent date for the gas supply agreement has been delayed from December 31, 2024, to February 4, 2025.
Operational Update
- The condition precedent date for the gas supply agreement has been extended from December 31, 2024 to February 4, 2025.
Sustainability Report
- A$20 million was received from sophisticated institutional investors.
- An additional A$4.6 million was received from existing shareholders through a share purchase plan.
Revised Presentation
- The company is seeking to raise the remaining equity funding through an offer to new and existing shareholders.
Annual Report Presentation
- The company is seeking to raise the remaining equity funding needed to commence construction.
Annual Report
- Arafura is actively seeking equity funding to reach a final investment decision on the Nolans Project.
Annual Report
- While the company is making progress, the timeline for reaching a final investment decision has been extended due to the complexities of securing funding in a challenging market environment.
Annual Report
- A $20 million institutional placement was completed.
- A share purchase plan is targeting an additional $7 million, with potential for up to $3 million in oversubscriptions.
Annual General Meeting Notice
- If all Placement Options are exercised, the Company will raise an additional $17,578,125 (before costs) to further progress the development of the Nolans Project and for general working capital purposes.
Share Purchase Plan Results
- The SPP raised $4.6 million (before costs).
- A previous placement raised $20 million.
Share Purchase Plan Results
- The SPP raised $4.6 million, which is less than the targeted $7 million.
Capital Raising Announcement
- A$20 million placement completed in two tranches.
- A$7 million target for the share purchase plan (SPP), with a potential for A$3 million in oversubscriptions.
General Meeting Results
- Share issuance under Tranche 1 and Tranche 2 of a placement.
- Share issuance under the SPP (including shortfall offer).
- Share issuance to directors under the SPP.
Share Purchase Plan Announcement
- Arafura Rare Earths is conducting a Share Purchase Plan (SPP) to raise A$7 million before costs.
- The company may accept oversubscriptions up to A$3 million.
- The SPP offer price is A$0.16 per new share.
Prospectus
- The company may offer SPP Shortfall Shares to specific investors if the SPP does not reach its target of $7 million.
- The company has conditional approval for US$775 million in senior debt facilities, an additional US$80 million for a cost overrun facility (COF) and a further US$200 million in the form of a standby liquidity facility (SLF).
Gas Sales Agreement Announcement
- The condition precedent date of the Arafura GSA has been extended by five months to December 31, 2024.
- The start date of the Arafura GSA has been deferred by two years to January 1, 2028.
- The NGP is not expected to reopen until later this year.
Gas Sales Agreement Announcement
- The Arafura GSA supply start date has been deferred by two years to January 1, 2028.
- The Northern Gas Pipeline (NGP) is not expected to re-open until later this year.
Announcement and Media Release
- The company will require further gas contracting and funding arrangements by Central to progress appraisal wells at Mereenie and Palm Valley.
Announcement and Media Release
- The Arafura GSA has been amended, deferring the supply start date by two years to January 1, 2028.
Trading Halt Request
- Arafura Rare Earths is completing the placement component of a capital raising.
- The trading halt is pending an announcement regarding the completion of this placement.
Quarterly Activities Report
- The company intends to execute a capital raising to secure the equity required for the project.
- Barrenjoey has been appointed as a third joint lead manager alongside UBS AG and Canaccord Genuity to assist in raising the equity.
Investor Presentation
- The sources and uses of funds includes adjustments for a 3-month delay in first production.
Investor Presentation
- The company is focused on securing equity, leveraging strategic nature of NdPr.
- The balance to be raised through offer to new and existing shareholders.
Project Funding Update
- The project includes an increase in ramp-up period (from 2 years to 3 years), and a 3-month delay in first production.
Project Funding Update
- The company needs to raise new equity to meet the balance of the Projects funding requirement.
- The COF equity component of US$80 million is targeted to be raised at the same time as the new equity.
Conference Presentation
- The company is planning a potential build-up of equity capital.
- Customer/strategic commitment will drive participation of financial groups.
- The balance to be raised through offer to new and existing shareholders.
Quarterly Activities Report
- The company intends to execute a capital raising when debt financing with key credit approvals is in place.
- The company is targeting a substantial portion of the equity requirement via cornerstone investors ahead of launching a public equity raising with institutions and retail investors.
Conference Presentation
- The company is planning a potential build-up of equity capital.
- The company has appointed Joint Lead Managers.
- The company is seeking customer/strategic commitment to drive participation of financial groups.
- The company is planning to raise capital through an offer to new and existing shareholders.
Disclaimer: This summary was generated by artificial intelligence and its accuracy is not guaranteed. The information provided here is for general informational purposes only and does not constitute financial advice, recommendation, or endorsement of any kind. It may contain errors or omissions. You should not rely on this information to make financial decisions. Always seek the advice of a qualified financial professional before making any investment or financial decisions. Use of this information is at your own risk.