Milling Started at Three Mile Hill. Target 40,000 Tonnes.
Summary
- Milling commenced at the Three Mile Hill Plant on November 20, 2024, processing ore from the Jeffreys Find Gold Mine.
- Approximately 25,000 tonnes of ore were on the pad at the start, with a target of at least 40,000 tonnes for the initial milling campaign.
- The first gold pour is anticipated within seven days of commencing operations.
- Auric expects to receive cash distributions in December 2024, with potential for further distributions in early 2025.
- The joint venture partner, BML, aims to process up to 75,000 tonnes in this first campaign, depending on haulage conditions.
- BML is also processing an estimated 142,000 tonnes at the Greenfields Mill, starting around November 28, 2024.
- By early 2025, approximately 420,000 tonnes are expected to be processed across both mills, completing the mining of Jeffreys Find Gold Mine.
Sentiment
Score: 7
Explanation: The announcement is largely positive, highlighting the commencement of milling and expected cash flows. However, the impact of rain on haulage introduces some uncertainty, lowering the overall score.
Positives
- Commencement of milling operations at Three Mile Hill Plant.
- First gold pour expected within seven days of commencing operations.
- Anticipated cash distributions to Auric in December 2024 and early 2025.
- Potential for significantly higher than target ore processing (up to 75,000 tonnes).
- Successful start to the relationship with Focus Minerals Ltd.
Negatives
- Haulage slowed by heavy rain.
- The success of the project is dependent on BML's ability to deliver sufficient ore to the mill.
Risks
- Heavy rain may disrupt haulage and impact the amount of ore processed.
- The success of the project is dependent on BML's ability to deliver sufficient ore to the mill.
- Uncertainties associated with forward-looking statements regarding future cash distributions and ore processing volumes.
Future Outlook
Auric expects cash distributions in December 2024 and early 2025. By early 2025, approximately 420,000 tonnes are expected to be processed across both mills, completing the mining of Jeffreys Find Gold Mine.
Management Comments
- 'Were off and running at Three Mile Hill.'
- 'If BML can feed the mill then the door is open to process 75,000 tonnes in this first campaign at Three Mile Hill. Haulage has been slowed down by heavy rain.'
- 'A great way to start our relationship with Focus Minerals Ltd.'
- 'The mill has confirmed there will be weekly gold pours for the campaign, with the first pour shortly.'
- 'There are approximately 50,000 tonnes of ore on the ROM Pad at Jeffreys Find ready to haul to Three Mile Hill Plant to fulfill the initial parcel.'
- 'We are expecting further cash distributions to Auric in December. We are in a fast forward mode to complete Jeffreys Find Gold Mine.'
Industry Context
This announcement reflects the ongoing activity in the Australian gold mining sector. The collaboration between Auric Mining and BML Ventures, utilizing the Three Mile Hill Plant owned by Focus Minerals, highlights the increasing trend of joint ventures and partnerships within the industry to optimize resource utilization and reduce operational costs.
Next Steps
- First gold pour within seven days.
- Cash distribution to Auric in December 2024.
- Completion of Jeffreys Find Gold Mine in early 2025.
Key Dates
- November 17, 2024: Photo of Jeffreys Find Pit taken
- November 20, 2024: Milling commenced at Three Mile Hill Plant
- November 28, 2024: Estimated start date for BML's processing at Greenfields Mill
- December 2024: Auric expects cash distributions
- Early 2025: Expected completion of mining at Jeffreys Find and further cash distributions to Auric
Keywords
Filings with Classifications
Investor Presentation
- The Jeffreys Find Gold Mine has significantly exceeded expectations by generating over $120 million in gold sales with a low acquisition and development cost of approximately $1.5 million.
- The estimated final cash distribution to Auric from Jeffreys Find of $11.5 million to $12.5 million is a strong financial outcome.
- The company's proforma financial estimates for FY2025 show substantial growth in total revenue to $24 million and net profit before tax to $13 million, indicating a very positive outlook.
Operational Update
- The project is expected to yield a 'bumper final payday' with Auric anticipating around $4.0 million from this campaign.
- Auric expects to bank more than $17 million in total from its profit share, described as a 'game changer' for the company.
- The target of 2,750 ounces from the final campaign is considered an 'impressive result'.
Commercial Agreement Announcement
- The execution of the toll milling and ore purchase agreement is a significant positive step, enabling the company to monetize gold from the Starter Pit and generate substantial cash flow.
Acquisition Update
- The Wardens Court hearing, originally due on 4 July 2025, has been further adjourned to 1 August 2025, delaying the resolution of a key condition precedent for the acquisition.
Acquisition Update
- The Wardens Court hearing, which is a condition precedent for the acquisition, was further adjourned from 4 July 2025 to 1 August 2025, indicating a delay in the acquisition process.
Annual General Meeting Presentation
- Net Profit Before Tax increased by a significant 212% from FY 2023 to FY 2024.
- Total Revenue grew by a substantial 76% in FY 2024.
- The Jeffreys Find Mine is projected to yield over $15 million in cash returns from a $1.5 million investment, indicating exceptional profitability.
- Total Assets and Net Current Assets also showed strong growth of 62% and 135% respectively.
Capital Raise Presentation
- The document is a capital raise presentation.
- The total allocation of the capital raising is $6,660,000.
- The funds are intended for the Burbanks Gold Facility and Lindsays Project.
Trading Halt Request
- Auric Mining is planning a capital raising.
- The details of the capital raising will be announced after the trading halt is lifted.
Legal Update
- The company is facing legal action, which introduces uncertainty and potential financial strain.
Annual Report
- The company's net profit before tax increased by over 300% compared to the previous year, indicating a significant improvement in financial performance.
Notice of Annual General Meeting
- The company is seeking approval for a 7.1A mandate, allowing it to issue up to 10% of its issued capital without further shareholder approval.
- Funds raised from the 7.1A Mandate will be used for acquisitions, exploration, development, and working capital.
Project Update
- The due diligence period for the Lindsays Gold Project has been extended.
Annual Report
- The company's net profit before tax increased by 212% compared to the previous year, indicating a significant improvement in profitability.
- Total revenue increased by 76%, demonstrating strong growth in sales.
- Adjusted net profit before tax increased by 101%, reflecting improved operational efficiency.
Corporate Presentation
- Stage Two gold production at Jeffreys Find has surpassed $100 million in revenue, exceeding initial expectations.
Announcement
- The settlement date will be changed to a date yet to be agreed, indicating a delay in the original timeline.
Operational Update
- The gold sales exceeded $100 million, surpassing initial expectations.
- The average gold price achieved was significantly higher than the initial estimate of A$2,600 per ounce.
Announcement
- The due diligence timeframe for the exclusive right to purchase the Burbanks Plant has been extended.
Quarterly Activities Report
- The company exceeded expectations with gold sales of $58.7 million at an average price of $3,952 per ounce.
- The Munda project has progressed faster than expected with the definition of an Ore Reserve and a clear path to mining.
- The acquisition of the Burbanks Mill at a discounted price is a positive development.
Quarterly Report
- The company reported a positive operating cash flow, which is better than many exploration companies that often report negative cash flow.
Production Update
- The company has exceeded expectations in terms of gold sales and ore processing compared to Stage One.
- The average gold price achieved is higher than previous sales, leading to increased revenue.
- The company has received significant interim cash distributions, indicating strong financial performance.
Operational Update
- The company's gold sales for 2024 have exceeded the previous year's total, indicating better than expected performance.
Acquisition Announcement
- The acquisition price is a substantial discount to current and replacement values.
- The acquisition will enable Auric to process its own ore, reducing reliance on third-party toll milling.
- The potential to upgrade the plant's capacity offers significant growth opportunities.
Clarification Announcement and Pre-Feasibility Study
- The upfront project capital cost for the starter pit is $6.5M.
- Any delay to the treatment of ore via toll milling leads to a requirement for working capital of $8.3M, including a 35% contingency.
Resource Update
- The updated resource estimate shows a slight reduction in grade compared to the previous estimate.
Capital Raise Announcement
- Auric Mining Limited is raising AUD 45,000 through the issue of 300,000 ordinary shares at AUD 0.15 per share.
Exploration Update
- The results are worse than expected due to the high AISC of $2,635 per ounce compared to industry averages, a lower than average gold recovery rate, and a very short mine life for the Starter Pit.
Exploration Update
- Any delay to the treatment of ore via toll milling leads to a requirement for working capital, including a 35% contingency, $8.3M.
Exploration Update
- The updated resource estimate shows a slight reduction in estimated gold grade compared to the previous estimate from January 2022.
Operational Update
- Heavy rain has slowed down the haulage of ore to the Three Mile Hill Plant, potentially impacting the overall processing timeline.
Exploration Update
- The drilling results exceeded expectations, revealing high-grade gold intercepts at the Fugitive Prospect and opening a new exploration target at Anomaly 37.
Quarterly Report
- The Munda Gold Project's timeline has been delayed due to DEMIRS requiring a Mining Proposal for a larger area than initially planned.
Quarterly Report
- The Jeffreys Find gold mine's second processing campaign exceeded expectations, generating significantly higher revenue than anticipated.
Operational Update
- The securing of a toll milling agreement with Focus Minerals for a significant amount of ore surpasses previous expectations and ensures expedited cash flow for Auric.
Half Year Financial Report
- Auric Mining reported a net profit for the half-year, a significant improvement from the previous year's loss, exceeding expectations given the previous year's performance.
Exploration Update
- The aircore drilling results exceeded expectations by confirming high-grade gold intersections at the Fugitive Prospect and identifying additional promising targets at the Anomaly 37 Prospect.
Quarterly Cash Flow Report
- The document includes questions about the entity's plans to raise further cash to fund its operations if it has less than 2 quarters of funding available.
- This suggests a potential need for a capital raise in the future.
Quarterly Cash Flow Report
- The company's net cash from operating activities was negative, indicating it spent more than it earned from operations.
- The company has negative cash available for future operating activities, suggesting potential funding challenges.
Production Update
- The company expects cash surpluses well in excess of what they had budgeted and anticipated due to the increasing gold price.
Missing type for ID: 5160
- ASX:AWJ announces better than expected results.
Production Update
- The average selling price of gold was $543 per ounce better than last year.
Quarterly Activities Report
- The company is targeting to mine 300,000 tonnes of ore in 2024, significantly more than the 176,000 tonnes processed in 2023.
Notice of Annual General Meeting
- The company is seeking approval for a 7.1A mandate, which would allow it to issue up to an additional 10% of its issued capital without further shareholder approval.
- The funds raised from these equity securities would be used for various purposes, including acquisitions, exploration, development, and working capital.
Annual Report
- The company reported a profit after income tax expense for the year attributable to the owners of Auric Mining Limited of $1,313,644 compared to a loss of $1,106,692 in the prior year.
Disclaimer: This summary was generated by artificial intelligence and its accuracy is not guaranteed. The information provided here is for general informational purposes only and does not constitute financial advice, recommendation, or endorsement of any kind. It may contain errors or omissions. You should not rely on this information to make financial decisions. Always seek the advice of a qualified financial professional before making any investment or financial decisions. Use of this information is at your own risk.