Exploration Update


Ramaco Resources details significant advancements and strong economic viability for its Brook Mine rare earth and critical minerals project, including pilot plant construction and updated financial assessments.

Better than expectedThe Preliminary Economic Assessment (PEA) by Fluor Corporation confirmed strong technical and economic viability with an initial Net Present Value (NPV) of up to $1.2 billion and an Internal Rate of Return (IRR) of 38%.An upsized case, increasing coal tonnage, projects an NPV of $5.1 billion and an IRR greater than 150%, significantly enhancing the project's economic potential beyond initial expectations.The Department of War's Defense Logistics Agency (DLA) signed an offtake to purchase scandium at over $6.2 million a ton, which is two-thirds higher than the $3.75 million level used in current economic modeling, indicating a higher market value than previously anticipated.

Summary

  • The Brook Mine, located in northern Wyoming, is believed to host the largest unconventional deposit of rare earth elements (REEs) in the United States, with high concentrations of magnetic REEs such as neodymium, praseodymium, terbium, and dysprosium.
  • The mine spans nearly 16,000 acres, with approximately 4,500 acres fully permitted for mining; the permit was renewed for a second 5-year term in July 2025.
  • Ramaco officially broke ground on the Brook Mine on July 11, 2025, and has actively mined the Monarch seam, accumulating sufficient coal and carbonaceous ore to supply the near-term needs of the pilot processing facility.
  • The pilot processing facility is currently under construction, with groundbreaking occurring in October 2025, and is expected to be operational by mid-2026.
  • Weir International's 2025 Technical Report Summary confirmed an inferred resource of approximately 1.4 million tons of total rare earth oxide (TREO).
  • The deposit also contains high-value critical minerals including gallium, germanium, and scandium, with the project having the potential to be the nation's leading producer of natural scandium.
  • The Department of War's Defense Logistics Agency (DLA) signed an offtake to purchase 6.4 metric tons of scandium at over $6.2 million per ton, significantly higher than the $3.75 million level used in current economic modeling.
  • A Preliminary Economic Assessment (PEA) by Fluor Corporation confirmed technical and economic viability, with an initial estimated Net Present Value (NPV) of up to $1.2 billion and an Internal Rate of Return (IRR) of 38%.
  • An upsized case, increasing coal tonnage from 2 million to 5 million tons per year, projects an NPV of $5.1 billion and an IRR greater than 150%, with REE and critical mineral production increasing from ~1,240 to ~3,400 tons per year.
  • Ramaco was awarded a $6.1 million matching grant from the Wyoming Energy Authority to help design, construct, and equip the pilot processing facility.
  • Hatch Ltd. has been retained to develop the pilot processing plant flow sheet and lead the Pre-Feasibility Study (PFS), anticipated to be delivered by mid-2026.
  • The U.S. Department of Energy's National Energy Technology Laboratory (NETL) was involved in the original discovery and continues to partner with Ramaco on scientific and engineering aspects, including applying its GAIA artificial intelligence platform for REE mapping.

Sentiment

Score: 9

Explanation: The filing presents a highly positive outlook for the Brook Mine project, backed by strong economic assessments (NPV up to $5.1 billion, IRR >150% in upsized case), significant government grants ($6.1 million), and strategic partnerships (NETL, DLA). Operational milestones like groundbreaking and pilot plant construction are on schedule, and the project addresses critical national supply chain needs.

Positives

  • Discovery of what is believed to be the largest unconventional rare earth element (REE) deposit in the United States at the Brook Mine.
  • High concentrations of magnetic REEs (neodymium, praseodymium, terbium, dysprosium) and critical minerals (gallium, germanium, scandium) found in the deposit.
  • Mining permit renewed for a second 5-year term in July 2025, affirming compliance with environmental and operational standards.
  • Active mining commenced on July 11, 2025, with sufficient ore stockpiled by October 2025 to supply the near-term needs of the pilot processing facility.
  • Pilot processing plant construction is underway, with groundbreaking in October 2025 and expected operation by mid-2026, demonstrating project advancement.
  • Independent validation by Weir International confirmed 1.4 million tons of total rare earth oxide (TREO) in the global inferred resource.
  • Potential to become the nation's leading producer of natural scandium, a critical mineral for which the U.S. is 100% import-reliant.
  • Secured an offtake agreement with the Department of War's Defense Logistics Agency (DLA) for scandium at over $6.2 million per metric ton, significantly above current modeling prices.
  • Strong economic viability confirmed by Fluor's Preliminary Economic Assessment (PEA), with an initial NPV of up to $1.2 billion and IRR of 38%.
  • An upsized case for the project projects an NPV of $5.1 billion and an IRR greater than 150%, indicating substantial long-term value.
  • Received a $6.1 million matching grant from the Wyoming Energy Authority, demonstrating state-level support and validation.
  • Strategic partnerships with U.S. Department of Energy's NETL for discovery, scientific expertise, and ongoing research, bolstering project credibility and innovation.
  • The unconventional nature of the deposit offers potentially more accessible, cost-effective, and environmentally responsible REE recovery compared to traditional hard-rock mining, with minimal radioactive content.
  • The project's 'basket price' based on NdPr equivalent grade is more than 10X higher than the industry trend for its ppm TREO, indicating superior value per unit of rare earth content.

Risks

  • Actual results may differ materially from forward-looking statements due to various risks and uncertainties.
  • Unexpected delays in current mine development activities could impact project timelines.
  • The ability to successfully ramp up production at complexes in accordance with growth initiatives is not assured.
  • Failure of sales commitment counterparties to perform could negatively affect revenue.
  • Increased government regulation of coal in the United States or internationally poses a risk.
  • The impact of tariffs imposed by the United States and foreign governments could affect market conditions.
  • A further decline of demand for coal in export markets and underperformance of railroads could impact the company's core business.
  • There is no assurance that the company will be able to successfully develop the Brook Mine REE/CM project, including whether exploration targets and estimates will be realized.
  • Uncertainty exists regarding the timing of the initial production of rare earth concentrates.
  • The successful development of a pilot and ultimately a full-scale commercial processing facility is not guaranteed.
  • Mineral resources may not be classified as mineral reserves, and inferred mineral resources have a high degree of uncertainty regarding their existence and economic viability.
  • Rare earth and critical minerals is a new initiative for the company, with heightened risks and uncertainties, and no assurance of successful commercial-scale mine development.
  • The company has little to no demonstrated track record of commercial, operational, or financial success outside of its core business, adding to the risks of this new venture.
  • Estimates derived from technical report summaries and preliminary economic analyses are subject to revision, which may be material, with additional data and analysis.

Future Outlook

Ramaco Resources is actively working on plans to expand coal production and increase the permitted acreage at the Brook Mine, engaging with state and federal agencies to expedite permitting approvals. Additional mining activity is expected to meet future pilot or commercial processing needs and coal sales demand. The pilot processing facility is anticipated to begin initial operation in mid-2026, allowing potential customers to test various oxides. A Pre-Feasibility Study (PFS) is expected by mid-2026, and the company plans continued collaborative research with NETL on REE processing, ore deposit modeling, and commercialization strategies. The project is expected to play a key role in establishing a secure, domestic supply chain for strategic minerals in the U.S.

Management Comments

  • The FAQ reflects Ramaco's ongoing commitment to transparency and its desire to keep the public and shareholders informed about the unique and transformative nature of the project.
  • The mining activity marked the launch of the first new rare earth mine in the United States in more than 70 years and the first new coal mine in Wyoming in more than 50 years.
  • The mine is expected to play a key role in helping to establish a secure, domestic supply chain for strategic minerals in the U.S.
  • The Brook Mine project has the potential to be the nation's leading producer of natural scandium.
  • Our plan is to upsize the amount of REEs and Critical Minerals getting produced from the Brook Mine.

Industry Context

The Brook Mine project directly addresses the critical national need for a secure, domestic supply chain of rare earth elements (REEs) and critical minerals, particularly given the U.S.'s 100% reliance on imports for scandium, primarily from China. This initiative is strategically important for advanced technologies and national defense, aligning with government efforts to reduce foreign dependency. The project's unconventional deposit type, hosted in coal seams, offers a potentially more accessible, cost-effective, and environmentally responsible alternative to traditional hard-rock mining, which often faces challenges with elevated radioactive elements and lower recovery rates. The high 'basket price' of the Brook Mine's REE and critical mineral mix, significantly exceeding industry trends for similar TREO grades, positions it competitively against deposits dominated by lower-value elements like lanthanum and cerium.

Comparison to Industry Standards

  • The Brook Mine distinguishes itself from traditional hard rock mining by potentially offering a more accessible, cost-effective, and environmentally responsible pathway to rare earth element (REE) recovery.
  • Unlike hard rock deposits that are often accompanied by elevated radioactive elements, the Brook Mine's REEs are hosted in soft carbonaceous strata and coal seams with minimal radioactive content.
  • Comparing the Brook Mine's basket price on an NdPr equivalent grade, it is more than 10X higher than the industry trend for its ppm TREO, indicating a superior value proposition.
  • Typical higher ppm TREO deposits are often dominated by low-value lanthanum (La) and cerium (Ce) (70% to more than 80% La and Ce), which require significant cost to remove, a challenge less pronounced for the Brook Mine.
  • Hard rock deposits often lose 35-45% of rare earths to tails prior to extraction, resulting in lower overall recoveries compared to the Brook Mine's expected flowsheet, which aims for higher recovered value per TREO grade.
  • The Department of War's Defense Logistics Agency (DLA) signed an offtake to purchase scandium at over $6.2 million a ton, which is two-thirds higher than the $3.75 million level used in current economic modeling, highlighting a premium market valuation for this specific critical mineral compared to internal estimates and general market trends.

Stakeholder Impact

  • Shareholders: Potential for significant value creation due to strong economic projections (NPV up to $5.1 billion, IRR >150%) and the strategic importance of the project in a critical minerals market.
  • U.S. Government/National Defense: Establishment of a secure, domestic supply chain for strategic minerals, reducing reliance on foreign sources (e.g., China) for REEs and scandium, thereby enhancing national security.
  • Wyoming Economy: Creation of new jobs and economic development in Sheridan County through mining operations and processing facilities, supported by state grants.
  • Customers (potential): Access to domestically sourced, high-purity rare earth oxides and critical minerals, particularly for advanced technologies and defense industries, ensuring supply chain resilience.
  • Employees: Creation of new employment opportunities in mining, processing, and related technical fields.

Next Steps

  • Actively work on plans to expand coal production and increase the size of the permitted acreage at the Brook Mine.
  • Engage with state and federal agencies to secure expanded permit authority, including reviewing recent Presidential and Secretary Executive Orders to expedite and simplify the permitting approval process.
  • Conduct additional mining activity as needed to meet future pilot or commercial processing needs and coal sales demand.
  • Begin initial operation of the pilot processing facility in mid-2026 to allow potential customers to test various oxides.
  • Hatch Ltd. to deliver the Pre-Feasibility Study (PFS) for the Brook Mine rare earth and critical minerals project by mid-2026.
  • Continue collaborative research with NETL on REE processing, ore deposit modeling, and commercialization strategies under a Cooperative Research and Development Agreement (CRADA).

Key Dates

DateDescription
July 1, 2025Ramaco released a Summary Preliminary Economic Assessment (PEA) for the Brook Mine via a Form 8-K filing and a shareholder letter.
July 11, 2025Ramaco officially broke ground on the Brook Mine in Sheridan, Wyoming.
July 2025Wyoming Department of Environmental Quality's Land Quality Division renewed Ramaco's mining permit for a second 5-year term.
October 2025Ramaco had mined sufficient projected quantities of coal and carbonaceous ore to meet near-term needs for the pilot processing facility.
October 2025Ramaco officially broke ground on the facility for its pilot processing plant and laboratory.
October 31, 2025Date of Report (earliest event reported) for the Form 8-K filing.
Mid-2026Pilot plant expected to begin initial operation.
Mid-2026Pre-Feasibility Study (PFS) anticipated to be delivered by Hatch Ltd.

Recommendation

strong buy

The filing reveals exceptionally strong economic projections for the Brook Mine project, with an upsized case Net Present Value (NPV) of $5.1 billion and Internal Rate of Return (IRR) exceeding 150%, significantly de-risking the project. The strategic importance of establishing a domestic supply chain for critical rare earth elements and scandium, coupled with substantial government support and a high-value offtake agreement with the Defense Logistics Agency (DLA), positions Ramaco Resources for substantial growth. Operational progress, including active mining and pilot plant construction, further reinforces confidence in the project's execution. These factors collectively indicate a compelling investment opportunity.

Keywords

Rare Earth Elements, Critical Minerals, Brook Mine, Ramaco Resources, METC, Wyoming, Scandium, Neodymium, Praseodymium, Dysprosium, Terbium, Gallium, Germanium, Mining, Pilot Plant, Domestic Supply Chain, Energy Transition, National Defense, SEC Filing

Disclaimer:The information provided here is for general informational purposes only and does not constitute financial advice, recommendation, or endorsement of any kind. It may contain errors or omissions. You should not rely on this information to make financial decisions. Always seek the advice of a qualified financial professional before making any investment or financial decisions. Use of this information is at your own risk.