10-Q: Eversource Energy Reports First Quarter 2024 Results, Reaffirms Guidance

Sentiment:

Quarterly Report


Eversource Energy announced its first quarter 2024 financial results, reporting earnings of $1.49 per share and reaffirming its full-year earnings guidance and long-term growth rate.

Capital raiseEversource issued 1,292,892 common shares in the first quarter of 2024, resulting in proceeds of $75.4 million, net of issuance costs.Eversource parent has a $2.00 billion commercial paper program allowing Eversource parent to issue commercial paper as a form of short-term debt.NSTAR Electric has a $650 million commercial paper program allowing NSTAR Electric to issue commercial paper as a form of short-term debt.On February 8, 2024, the NHPUC approved PSNHs request for authorization to issue up to $300 million in long-term debt through December 31, 2024.On May 1, 2024, the DPU approved NSTAR Electrics request for authorization to issue up to $2.4 billion in long-term debt through December 31, 2026.

Summary

  • Eversource Energy reported net income attributable to common shareholders of $521.8 million, or $1.49 per share, for the first quarter of 2024, compared to $491.2 million, or $1.41 per share, for the same period in 2023.
  • The company reaffirmed its 2024 non-GAAP earnings guidance range of $4.50 to $4.67 per share, excluding the impact of expected offshore wind asset sales and related transaction costs.
  • Eversource also reaffirmed its long-term EPS growth rate projection of 5 to 7 percent through 2028.
  • Cash flows from operating activities were $291.3 million, up from $69.2 million in the first quarter of 2023.
  • Investments in property, plant, and equipment totaled $1.15 billion, compared to $977.1 million in the prior year's quarter.
  • The company issued $1.35 billion in new long-term debt during the quarter.
  • Eversource is progressing with the planned sale of its offshore wind investments, with agreements in place to sell its interests in the South Fork Wind, Revolution Wind, and Sunrise Wind projects.
  • The sale of its 50 percent interest in an uncommitted lease area to rsted was completed in September 2023 for $625 million.
  • The company expects to receive approximately $1.1 billion from the sale of South Fork Wind and Revolution Wind to Global Infrastructure Partners (GIP).
  • Eversource and rsted executed an agreement to sell Eversource's 50 percent interest in Sunrise Wind to rsted, with the sale expected to be completed later this year.
  • The company is also conducting an exploratory assessment of a potential sale of its water distribution business.

Sentiment

Score: 7

Explanation: The sentiment is moderately positive. While revenue is down, earnings are up, and the company is executing a strategic shift to de-risk its portfolio. The reaffirmation of guidance provides stability.

Positives

  • Earnings per share increased from $1.41 to $1.49 year-over-year.
  • Cash flows from operating activities significantly improved.
  • The company is progressing with the sale of its offshore wind assets, which is expected to generate significant cash proceeds.
  • The company reaffirmed its earnings guidance and long-term growth rate projection.

Negatives

  • Operating revenues decreased from $3,795.6 million to $3,332.6 million year-over-year.
  • Eversource parent and other companies losses increased $17.8 million in the first quarter of 2024, as compared to the first quarter of 2023, due primarily to higher interest expense and the absence of a benefit in the first quarter of 2023 from the liquidation of Eversource parents equity method investment in a renewable energy fund, partially offset by the absence of a charitable contribution made with a portion of the proceeds from the liquidation in the first quarter of 2023.

Risks

  • The company's ability to complete the offshore wind investments sales process on the timelines, terms and pricing it expects is subject to various closing conditions and regulatory approvals.
  • Variability in the projected construction costs of the offshore wind projects could impact the economics of the sales.
  • Delays in constructing Revolution Wind could impact the economics associated with the purchase price adjustment.
  • The company is subject to risks related to cyberattacks, economic conditions, regulatory actions, weather patterns, and other unforeseen factors.

Future Outlook

Eversource reaffirmed its 2024 non-GAAP earnings guidance range of $4.50 to $4.67 per share and its long-term EPS growth rate projection of 5 to 7 percent through 2028.

Industry Context

The announcement reflects a strategic shift in Eversource's focus, moving away from direct ownership of offshore wind projects towards a regulated utility model. This aligns with a broader industry trend of utilities de-risking their portfolios and focusing on core operations.

Comparison to Industry Standards

  • Comparing Eversource's Q1 2024 EPS of $1.49 to peers like NextEra Energy (NEE) and Duke Energy (DUK) provides a benchmark for performance within the utility sector.
  • The reaffirmed long-term EPS growth rate of 5-7% is a key metric for investors, and comparing this to the projected growth rates of similar utilities helps assess Eversource's competitive positioning.
  • The strategic decision to sell offshore wind assets mirrors moves by other utilities to reduce exposure to development risks and focus on regulated earnings, such as Ørsted's (ORSTED.CO) recent restructuring.

Legal Proceedings

  • The Yankee Companies have filed complaints against the DOE in the Court of Federal Claims seeking monetary damages resulting from the DOE's failure to accept delivery of, and provide for a permanent facility to store, spent nuclear fuel pursuant to the terms of the 1983 spent fuel and high-level waste disposal contracts between the Yankee Companies and the DOE.
  • Four separate complaints were filed at the FERC by combinations of New England state attorneys general, state regulatory commissions, consumer advocates, consumer groups, municipal parties and other parties (collectively, the Complainants).

Stakeholder Impact

  • Customers will see changes in their rates due to the base distribution rate increase at NSTAR Electric and the rate adjustments at CL&P.
  • Shareholders will benefit from the company's strategic shift and reaffirmed earnings guidance.
  • Employees may be affected by the company's restructuring and asset sales.

Next Steps

  • Complete the sale of offshore wind assets.
  • Obtain regulatory approvals for the sale of South Fork Wind and Revolution Wind to GIP.
  • Finalize the OREC contract with NYSERDA for Sunrise Wind.
  • Continue construction of Revolution Wind and Sunrise Wind projects.
  • Obtain BOEM final approval of the Sunrise Wind Construction and Operations Plan (COP).
  • Address the Courts findings on the remand of the MISO FERC opinions or any potential associated impact on the NETOs four pending ROE complaint cases.
  • Continue to monitor developments in the PBR proceeding, and at this time, we cannot predict the ultimate outcome of this proceeding and the resulting impact to CL&P.
  • Continue to monitor developments in the PURA proceeding, and at this time, we cannot predict the ultimate outcome of this proceeding and the resulting impact to CL&P.
  • Continue to monitor developments in the FERC Notice of Proposed Rulemaking on Transmission Incentives, and at this time, Eversource cannot predict the ultimate outcome of these proceedings, including possible appellate review, and the resulting impact on its transmission incentives.

Key Dates

DateDescription
2005NETOs' base ROE of 11.14 percent that had been utilized since 2005
2011-10-01First FERC ROE complaint filed
2012-12-27Second FERC ROE complaint filed
2014-07-31Third FERC ROE complaint filed
2014-10-16FERC issued Opinion No. 531-A, setting base ROE at 10.57 percent and incentive cap at 11.74 percent for the first complaint period
2016-04-29Fourth FERC ROE complaint filed
2017-04-14FERC order vacated by U.S. Court of Appeals for the D.C. Circuit
2018-05PSNH Funding issued $635.7 million of securitized RRBs
2018-10-16FERC issued an order on all four complaints describing how it intends to address the issues that were remanded by the Court
2019-11-21FERC issued Opinion No. 569 affecting the two pending transmission ROE complaints against the Midcontinent ISO (MISO) transmission owners
2019-12-23The NETOs filed supplementary materials in the NETOs' four pending cases to respond to this new methodology because of the uncertainty of the applicability to the NETOs' cases.
2020-03-20FERC issued a Notice of Proposed Rulemaking (NOPR) on transmission incentives.
2020-05-21The FERC issued its order in Opinion No. 569-A on the rehearing of the MISO transmission owners' cases, in which FERC again changed its methodology for determining the MISO transmission owners' base ROEs.
2020-07-01Eversource filed comments generally supporting the NOPR.
2020-07-31CL&P submitted to PURA its proposed $512 million Advanced Metering Infrastructure (AMI) investment and implementation plan.
2020-11-19The FERC issued Opinion No. 569-B denying rehearing of Opinion No. 569-A and reaffirmed the methodology previously adopted in Opinion No. 569-A.
2021-03-25Each of the Yankee Companies filed a fifth set of lawsuits against the DOE in the Court of Federal Claims resulting from the DOE's failure to begin accepting spent nuclear fuel for disposal covering the years from 2017 to 2020.
2021-04-15FERC issued a Supplemental NOPR that proposes to eliminate the existing 50 basis point return on equity for utilities that have been participating in a regional transmission organization (RTO ROE incentive) for more than three years.
2021-05-26PURA opened a proceeding to begin to evaluate and eventually implement performance-based regulation (PBR) for electric distribution companies.
2021-06-25The NETOs jointly filed comments strongly opposing FERCs proposal.
2021-07-26The NETOs filed Supplemental NOPR reply comments responding to various parties advocating for the elimination of the RTO Adder.
2021-08-17PURA issued a Notice of Request for an Amended EDC Advanced Metering Infrastructure Proposal.
2021-11-08CL&P submitted an Amended Proposal in response to this request with an updated schedule for the years 2022 through 2028, which included additional information as required by PURA.
2022-05-11Eversource entered into an equity distribution agreement pursuant to which it may offer and sell up to $1.2 billion of its common shares from time to time through an at-the-market (ATM) equity offering program.
2022-08-09The Court issued its decision vacating MISO ROE FERC Opinion Nos. 569, 569-A and 569-B and remanded to FERC to reopen the proceedings.
2022-08-29Aquarion Water Company of Connecticut (AWC-CT) filed an application with PURA to amend its existing rate schedules to address an operating revenue deficiency.
2022-12-16For the Sunrise Wind project, BOEM released its Draft EIS
2023-01-25PURA staff issued a proposal outlining a suggested portfolio of PBR elements for further exploration and potential implementation in the second phase of the proceeding.
2023-03-15PURA issued a final decision that rejected this request. In this decision, PURA ordered a decrease to total authorized revenues of $4.0 million effective March 15, 2023.
2023-03-21Eversources equity method investment in a renewable energy investment fund was liquidated by the funds general partner in accordance with the partnership agreement.
2023-03-25the State of Connecticut Superior Court issued a decision on the rate case appeal
2023-03-30AWC-CT filed an appeal on the decision and requested a stay of the decision with the State of Connecticut Superior Court.
2023-04-05The Court temporarily granted AWC-CTs request to stay
2023-04-26PURA issued a final decision on the first phase and identified various objectives to guide PBR development and evaluate adoption of a PBR framework.
2023-05-25Eversource announced that it had completed a strategic review of its offshore wind investments and determined that it would pursue the sale of its offshore wind investments.
2023-05-26the Court granted a permanent stay of certain orders affecting base rates, which will keep existing rates in place until the appeal is completed.
2023-07-01Effective July 1, 2023, the average NBFMCC rate changed to $0.00000 per kWh.
2023-09-07Eversource completed the sale of its 50 percent interest in an uncommitted lease area consisting of approximately 175,000 developable acres located 25 miles off the south coast of Massachusetts to rsted for $625 million in an all-cash transaction.
2023-09-15NSTAR Gas submitted its third annual PBR Adjustment filing
2023-10-30the DPU approved a $25.4 million increase to base distribution rates, of which, $15.5 million was associated with a base rate adjustment and the remainder for a prior period exogenous cost adjustment, for effect on November 1, 2023.
2023-10-31For Revolution Wind, the joint venture made its final investment decision to advance to full onshore and offshore construction and installation
2023-11-01NSTAR Gas base distribution rate increase effective
2023-11-16PURA issued a straw proposal in the first reopener that focused on revenue adjustment mechanisms.
2023-12-15For the Sunrise Wind project, BOEM released its Final EIS
2023-12-22CL&P initiated a docket seeking a prudency review of approximately $634 million of catastrophic storm costs for twenty-four weather events from January 1, 2018 to December 31, 2021.
2023-12-26the DPU approved a $104.9 million increase to base distribution rates effective January 1, 2024.
2023-12-29Eversource and other LDCs sought formal clarity from the DPU to fully understand the resulting impact to their natural gas businesses and the associated timing of any impacts.
2024-01-01Four of South Fork Winds twelve turbines were placed into service and met the project commercial operation date requirements under the power purchase agreement with LIPA.
2024-01-01NSTAR Electric base distribution rate increase effective
2024-01-03PURA issued a final decision regarding CL&Ps Advanced Metering Infrastructure investment and implementation plan
2024-01-18CL&P submitted a motion for reconsideration to PURA asking that the agency modify these aspects of the decision
2024-01-24rsted signed an agreement with Eversource to acquire Eversources 50 percent share of Sunrise Wind
2024-01-25Sunrise Wind submitted a proposal in the New York fourth offshore wind solicitation
2024-01-31Our Board of Trustees approved a common share dividend payment of $0.715 per share, paid on March 29, 2024 to shareholders of record as of March 5, 2024.
2024-02-08the NHPUC approved PSNHs request for authorization to issue up to $300 million in long-term debt through December 31, 2024.
2024-02-13Eversource announced that it executed an agreement to sell its existing 50 percent interests in the South Fork Wind and Revolution Wind projects to Global Infrastructure Partners (GIP).
2024-02-14PURA denied CL&Ps motion for reconsideration
2024-02-29Sunrise Wind was selected by NYSERDA for contract negotiation
2024-03-01PURA declined CL&Ps request stating that a rate amendment should be conducted as part of a rate case.
2024-03-05S&P revised the outlook from watch negative to negative for Eversource parent, CL&P, NSTAR Electric, and PSNH.
2024-03-06CL&P filed written comments citing four major problems associated with PURAs guidelines for recovery of the costs of AMI implementation
2024-03-13the court issued an order establishing a schedule to resolve pending discovery issues by June 10, 2024, after which the court will set dates for further proceedings in the DOE Phase V trial.
2024-03-14PURA issued a straw proposal in the second reopener docket which concentrates on performance mechanisms in a PBR framework.
2024-03-25the State of Connecticut Superior Court issued a decision on the appeal which dismissed nine, remanded back to PURA two, and partially remanded one of AWC-CTs twelve claims of error in its appeal.
2024-03-26For Sunrise Wind, the joint venture made its final investment decision to proceed with the project.
2024-03-28AWC-CT filed an appeal of the Connecticut Superior Court decision to the Connecticut Appellate Court and on April 8, 2024, requested the appeal move directly to the Connecticut Supreme Court for review.
2024-03-28PURA established a proceeding for the purpose of receiving and reviewing evidence of the costs reported by CL&P in response to catastrophic storms and pre-staging events occurring between 2018 and 2021.
2024-04-02the DPU issued an order responding to the request for clarification indicating that the LDCs shall implement the inclusion of a Non-Gas Pipeline Alternatives (NPA) analysis on all project authorizations effective immediately.
2024-04-10the U.S. Environmental Protection Agency announced the final regulation setting drinking water standards for six perand polyfluoroalkyl substances (PFAS) compounds.
2024-04-16PURA issued a procedural order directing Eversource and inviting all parties and intervenors to submit pre-filed testimony pertaining to AMI by May 14, 2024, and rebuttal testimony by May 29, 2024.
2024-04-17PURA issued an interim decision in CL&Ps Rate Adjustment Mechanisms (RAM) filing and approved rates for the six RAM components, with rates effective July 1, 2024 through April 30, 2025.
2024-04-18Eversource and rsted executed the equity and asset purchase agreement to sell Eversources 50 percent interest in Sunrise Wind to rsted
2024-05-01the DPU approved NSTAR Electrics request for authorization to issue up to $2.4 billion in long-term debt through December 31, 2026.
2024-05-01Our Board of Trustees approved a common share dividend payment of $0.715 per share, payable on June 28, 2024 to shareholders of record as of May 16, 2024.
2024-05-14PURA will receive pre-filed testimony pertaining to AMI
2024-05-29PURA will receive rebuttal testimony pertaining to AMI
2024-06-10schedule to resolve pending discovery issues
2024-07-31PURA's final decision is scheduled for July 31, 2024.
2024-Q4A final decision is expected in the fourth quarter of 2024.
2025final decisions expected in 2025
2025We expect the Revolution Wind project to be in-service in late 2025.
2026For Sunrise Wind, based on the current expected timing of BOEMs final approval and the start of offshore construction, we currently expect an in-service date in 2026.

Keywords

Eversource Energy, Financial Results, Offshore Wind, Earnings, Guidance, Debt, Capital Expenditures, Regulatory, Transmission, Distribution

Disclaimer:The information provided here is for general informational purposes only and does not constitute financial advice, recommendation, or endorsement of any kind. It may contain errors or omissions. You should not rely on this information to make financial decisions. Always seek the advice of a qualified financial professional before making any investment or financial decisions. Use of this information is at your own risk.